Slow progress on some systems delaying other elements of Trillium Line LRT prep: report
A report prepared for a joint meeting of Ottawa's Transit Commission and Light Rail Subcommittee suggests that slow progress on completing work on the signalling, train control, and communications systems on the Trillium Line is having a domino effect on other aspects of preparation.
The joint meeting will be held Thursday, in place of the previously scheduled LRT subcommittee meeting that was supposed to be held Monday.
- The information you need to know, sent directly to you: Download the CTV News App
- Sign up now for our nightly CTV News Ottawa newsletter
The report outlining progress on Stage 2 LRT says that some slower than anticipated progress on parts of Line 2 is leading to other delays.
"Schedule deviations with signal and train control, and some communication systems (cameras, building management systems, etc.), are progressing at a slower pace than initially anticipated," the report states. "TransitNEXT continues to work on system installation and testing and commissioning. Progress on this item continues but remains slow."
TransitNEXT is the wholly owned subsidiary of SNC Lavalin that has been contracted to build the Stage 2 north-south Trillium Line extension, which will extend service to Riverside South and the Ottawa International Airport.
The slow progress on the signal, train control, and communications systems is affecting training, staff recruitment, and maintenance readiness, the report says.
"These areas are experiencing ongoing challenges due to the slower than anticipated commissioning progress for the signaling and train control system. Impacts on the training program are being assessed and the teams are working closely together to find ways to maximize training hours."
The report says delays to infrastructure readiness and subsequent training delays would create "a requirement for additional time to prepare for launch," but it doesn't lay out any specific length of time that might be required.
Transit Services General Manager Renée Amilcar said in September that the train control system on the Trillium Line is "unique" and required "a lot more testing."
There are also delays with getting Building Code Services occupancy permits and Technical Standards and Safety Authority (TSSA) approvals for elevators because of wider system functionality and station readiness delays, the report says.
Line 2 is expected to open sometime in the spring of 2024. Construction was originally scheduled to be completed in August 2022, but was delayed until September 2023 with a projected launch in November. Amilcar said in September that a November launch was no longer possible, suggesting April 2024 as a possible window, though she refused to speculate on a firm launch date.
The report says work is still required on the Bowesville and Leitrim park-and-ride facilities and the Limebank Station bus platform. Construction of all 13 stations on the Trillium Line remains ongoing, with commissioning of electrical, mechanical, fire safety systems, and communication systems remaining.
In mid-November, Amilcar announced what she called a "key milestone", saying nine trains had been successfully tested on Line 2. That testing will continue over the winter months, the report for Thursday's joint meeting says.
"Critically, the plan going forward is to increase the number of operating hours of the trains in order to properly demonstrate sustainable reliability of the fleet and the systems. This period of additional running time, including through the winter, is critical to surfacing and correcting issues before the line opens for service."
City councillors on the two committees will meet at 9:30 a.m. Thursday.
In addition to a progress update on Stage 2 of LRT and the current state of the active bus and train fleet, heads of the unions that represent OC Transpo employees will address councillors and deliver a presentation on their members' issues. The unions include the Amalgamated Transit Union, locals 279 and 1760, the Canadian Union of Public Employees Local 5500, and the Civic Institute of Professional Personnel.
In 2022, Ottawa city council agreed to give the unions a once yearly platform at Transit Commission meetings, and to host two informal sessions between the Transit Commission, OC Transpo Management, and Union executives during the 2022-26 Term of Council. The first such session is expected to take place in 2024.
CTVNews.ca Top Stories
Canada to launch 'national action plan' to fight auto theft
The federal government is launching what it calls its 'national action plan' to combat auto thefts, which will include stronger penalties for thieves, and increased information sharing between police agencies, government officials and border enforcement.
U.S. Supreme Court rejects appeal from former Guantanamo detainee Omar Khadr
The U.S. Supreme Court on Monday rejected an appeal by a Canadian-born former Guantanamo detainee who was seeking to wipe away his war crimes convictions, including for killing a U.S. soldier in Afghanistan.
What is BORG drinking, and why is it a dangerous trend? An expert explains
If you've been to a party lately and haven't seen someone drinking a BORG, you're likely not partying with college students.
Iran's president and foreign minister die in helicopter crash at moment of high tensions in Mideast
Iranian President Ebrahim Raisi and the country's foreign minister were found dead Monday hours after their helicopter crashed in fog, leaving the Islamic Republic without two key leaders as extraordinary tensions grip the wider Middle East.
Michael Cohen says he stole from Trump's company as defence presses key hush money trial witness
Former Donald Trump attorney Michael Cohen admitted Monday to jurors in the Republican's hush money trial that he stole tens of thousands of dollars from Trump's company as defence lawyers seized on the star witness' misdeeds to attack his credibility.
The world's best airline is paying staff a bonus of 8 months' salary
Singapore Airlines will reward its employees with a bonus worth nearly eight months of salary, a person familiar with the matter told CNN on Friday.
Investors watching posts from 'Crypto King' in the wake of fraud, money laundering charges
Former investors of the self-styled “Crypto King” say they are watching his social media accounts and worried his displays of wealth are signs he’s spending their money, even now, as another large expense tied to Aiden Pleterski has triggered a previously unreported lawsuit.
Woman, 35, in critical condition after her truck collided with a Via Rail train near Montreal
A 35-year-old woman is in critical condition after the pick-up truck she was driving was struck by a Via Rail passenger train Monday morning in Quebec's Monteregie region.
Jury finds Andrei Donet guilty of second-degree murder in stabbing death of Montreal teen
A jury has found a 21-year-old man guilty of second-degree murder in the stabbing death of Montreal teenager Jannai Dopwell-Bailey outside his school in 2021.