Trillium Line will undergo 21 consecutive days of testing before launch
The city of Ottawa will require a longer trial run period for the new north-south Trillium Line before it launches, incorporating lessons learned from the launch of the Confederation Line nearly three years ago.
The city of Ottawa released the unredacted versions of the Stage 2 O-Train Confederation Line and Trillium Line Project Agreement Testing and Commission Schedules on Friday. The documents outline the testing and commission and trial running before launching Stage 2 of the LRT projects.
In a memo to council, Director of Rail Construction Program Michael Morgan said lessons learned from the commissioning and trial running of Stage 1 of the Confederation Line will be implemented into Stage 2 Trillium Line requirements.
"Staff applied various lessons learned from the testing and commissioning and trial running of the Line 1 Confederation Line into the Stage 2 Trillium Line extension requirements, including longer trial running period, improved performance criteria and inclusion of a systems integration verifier to oversee the works," Morgan said.
The Confederation Line will be required to undergo 12 consecutive days of testing before launch, while the Trillium Line from Bayview Station to Riverside South will undergo 21 consecutive days of testing.
Morgan says there will be a trial running period of 14 days for the Trillium Line, with an additional tests "during the 21 day period" that would include "a variety of failure management scenarios that could reasonably be expected to occur."
OC Transpo and Rideau Transit Group were required to conduct 12 days of testing before the Confederation Line opened from Blair Road to Tunney's Pasture in 2019. The city of Ottawa took possession of the Confederation Line on Aug. 23, 2019, 456 days after the initial deadline.
Here is a look at the Testing and Commission schedules for the Stage 2 LRT.
TRILLIUM LINE
TransitNEXT will be responsible for the testing and commissioning of the complete integrated system (civil infrastructure, systems, vehicles, etc.)
Morgan says TransitNEXT will conduct trial running when the integrated system infrastructure has been tested, when the complete fleet is fully tested and ready for messenger service, there are no outstanding defects affecting rail system functionality and all stations "are substantially complete with only Minor Deficiencies remaining."
The trial run length will be 21 days, with the trial run operating a full regular scheduled service on the full line for a 14-day period.
Additional tests during the 21-day period will include a variety of failure management scenarios that could "reasonably be expected to occur in regular revenue service," Morgan said.
The performance criteria is TransitNEXT achieving the Service Reliability Standard wherein 98.5 per cent on-time performance must be achieved over a 14-day period within the 21-day Trial Running period.
"TransitNEXT will demonstrate that the integrated system (vehicles, stations, and infrastructure) performs reliably through the Trial Running period such that the performance criteria for Trial Running are achieved and that would otherwise lead to zero performance deductions during the maintenance period," said the memo.
CONFEDERATION LINE
The city of Ottawa says Rideau Transit Group is responsible for the testing and commissioning of the complete integrated system (civil infrastructure systems, vehicles, etc.)
"RTG is responsible to conduct trial running when the integrated system has been tested and is essentially ready for revenue service," writes Morgan.
"Trial running will be the final step in confirming readiness for revenue service."
The 12 consecutive days of trial running will operate a full regular scheduled service on the full line using the peak and non-peak schedules for an "extended period," the city says.
"The tests will include a variety of failure management scenarios that could reasonably be expected to occur in regular revenue service," Morgan said.
The Confederation Line extension will run from Blair Road to Tenth Line Road in the east end, and from Tunney's Pasture to Algonquin College and Moodie Drive in the west end.
CTVNews.ca Top Stories
More than 115 cases of eye damage reported in Ontario after solar eclipse
More than 115 people who viewed the solar eclipse in Ontario earlier this month experienced eye damage after the event, according to eye doctors in the province.
Toxic testing standoff: Family leaves house over air quality
A Sherwood Park family says their new house is uninhabitable. The McNaughton's say they were forced to leave the house after living there for only a week because contaminants inside made it difficult to breathe.
Decoy bear used to catch man who illegally killed a grizzly, B.C. conservation officers say
A man has been handed a lengthy hunting ban and fined thousands of dollars for illegally killing a grizzly bear, B.C. conservation officers say.
B.C. seeks ban on public drug use, dialing back decriminalization
The B.C. NDP has asked the federal government to recriminalize public drug use, marking a major shift in the province's approach to addressing the deadly overdose crisis.
OPP responds to apparent video of officer supporting anti-Trudeau government protestors
The Ontario Provincial Police (OPP) says it's investigating an interaction between a uniformed officer and anti-Trudeau government protestors after a video circulated on social media.
An emergency slide falls off a Delta Air Lines plane, forcing pilots to return to JFK in New York
An emergency slide fell off a Delta Air Lines jetliner shortly after takeoff Friday from New York, and pilots who felt a vibration in the plane circled back to land safely at JFK Airport.
Sophie Gregoire Trudeau on navigating post-political life, co-parenting and freedom
Sophie Gregoire Trudeau says there is 'still so much love' between her and Prime Minister Justin Trudeau, as they navigate their post-separation relationship co-parenting their three children.
Last letters of pioneering climber who died on Everest reveal dark side of mountaineering
George Mallory is renowned for being one of the first British mountaineers to attempt to scale the dizzying heights of Mount Everest during the 1920s. Nearly a century later, newly digitized letters shed light on Mallory’s hopes and fears about ascending Everest.
Loud boom in Hamilton caused by propane tank, police say
A loud explosion was heard across Hamilton on Friday after a propane tank was accidentally destroyed and detonated at a local scrap metal yard, police say.