Trillium Line launch delayed until spring 2024
Passengers will not be boarding the Trillium Line until the spring of 2024, as construction continues on the new north-south light-rail transit line between Bayview Station and Riverside South.
Transit Services general manager Renee Amilcar says based on the progress to date, a possible launch in November is no longer possible.
"In order to be as cautious and prudent as possible, we believe it's the public interest to target a handover from the contractor as soon as possible, but to plan for opening the system to the public in spring 2024," Amilcar told the light-rail transit subcommittee meeting on Friday.
"This decision will provide city staff and the maintenance team with a longer runway to finalize training and fully exercise the system before it opens to the public."
- The information you need to know, sent directly to you: Download the CTV News App
- Sign up now for our nightly CTV News Ottawa newsletter
Amilcar wouldn't give a firm commitment on an opening date, but suggested the transit service is aiming for the launch of the Trillium Line in April.
Staff say final construction activity, testing and commissioning are "well underway" on the Trillium Line, but only five of the nine trains are currently operating during testing on the transit system.
TransitNext was contracted to build and maintain the Trillium Line between Bayview Station and Riverside South, with a spur to the Ottawa Airport.
Construction was originally scheduled to be completed in August 2022, but was delayed until September 2023. As of this summer, the target date for launch was November.
The LRT subcommittee received its first look at the scoreboard for the testing and preparations for launch, which looks at the status of all "critical elements" to launch the LRT system.
Staff say all the elements are currently at a "no-go" for launch.
"We are having some challenges and the progress isn't as quick as expected on systems, installation and testing and commissioning of those systems," Justin Kurosky, program manager of Trillium Line handover, told councillors.
Work to be completed include testing of the ventilation system in the tunnel in October, testing of the maintenance contractor's performance and final testing of the system with nine trains is "outstanding." Amilcar says OC Transpo is behind on training staff since only five trains started running on the Trillium Line last week.
- Sign up now for our nightly CTV News Ottawa newsletter
- The information you need to know, sent directly to you: Download the CTV News App
The committee was told on Friday that power has been connected at both Dow's Lake Station and South Keys station, and work is underway to commission the elevators and systems at the stations. The Hydro Ottawa strike was blamed for delays in connecting electricity to Dow's Lake and South Keys stations this summer.
Amilcar says the contractor is expected to finish the "majority of the work by the end of November," but there is the "possibility that some remaining work could slip further."
"Demonstrating nine trains in service is an important milestone in the process, but it is a more important to demonstrate that the service is reliable over an extended running time," Amilcar said. "This additional time, including during winter, will be used to further test, monitor and observe performance of the system."
Amilcar says the train control system for the Trillium Line is "unique," so OC Transpo and TransitNext "need a lot more testing."
"Knowing this, I'm asking that the test be even more numerous than we anticipated."
Building occupancy permits have not been issued for any of the 13 stations along the Trillium Line, which would allow public access for passenger service. Staff say all systems, including cameras, telephones, passenger information displays, intrusion access control and fire alarms, are 80 per cent installed and testing and commissioning is in progress.
When it comes to the park and ride facilities at Leitrim, Bowesville and Limebank stations, paving for the parking lots is scheduled for October.
Amilcar says the extended testing will ensure it is "ready for service" and will give staff a chance to look for any "latent or hidden defects."
"We acknowledge that our customers will be disappointed by this news, but we have heard from you very clearly that Ottawa doesn't want to see a system that has been rushed into service."
CTVNews.ca Top Stories
Canada to launch 'national action plan' to fight auto theft
The federal government is launching what it calls its 'national action plan' to combat auto thefts, which will include stronger penalties for thieves, and increased information sharing between police agencies, government officials and border enforcement.
U.S. Supreme Court rejects appeal from former Guantanamo detainee Omar Khadr
The U.S. Supreme Court on Monday rejected an appeal by a Canadian-born former Guantanamo detainee who was seeking to wipe away his war crimes convictions, including for killing a U.S. soldier in Afghanistan.
What is BORG drinking, and why is it a dangerous trend? An expert explains
If you've been to a party lately and haven't seen someone drinking a BORG, you're likely not partying with college students.
Iran's president and foreign minister die in helicopter crash at moment of high tensions in Mideast
Iranian President Ebrahim Raisi and the country's foreign minister were found dead Monday hours after their helicopter crashed in fog, leaving the Islamic Republic without two key leaders as extraordinary tensions grip the wider Middle East.
Michael Cohen says he stole from Trump's company as defence presses key hush money trial witness
Former Donald Trump attorney Michael Cohen admitted Monday to jurors in the Republican's hush money trial that he stole tens of thousands of dollars from Trump's company as defence lawyers seized on the star witness' misdeeds to attack his credibility.
The world's best airline is paying staff a bonus of 8 months' salary
Singapore Airlines will reward its employees with a bonus worth nearly eight months of salary, a person familiar with the matter told CNN on Friday.
Woman, 35, in critical condition after her truck collided with a Via Rail train near Montreal
A 35-year-old woman is in critical condition after the pick-up truck she was driving was struck by a Via Rail passenger train Monday morning in Quebec's Monteregie region.
Investors watching posts from 'Crypto King' in the wake of fraud, money laundering charges
Former investors of the self-styled “Crypto King” say they are watching his social media accounts and worried his displays of wealth are signs he’s spending their money, even now, as another large expense tied to Aiden Pleterski has triggered a previously unreported lawsuit.
Almost 2 months after it destroyed Baltimore's Key Bridge, the Dali cargo ship has been moved
The cargo ship Dali is being moved from the site of its catastrophic collision with the Francis Scott Key Bridge in a crucial step toward fully reopening the busy Port of Baltimore.