Stage 2 LRT work blamed for delayed Line 1 start in east end Saturday

An R1 bus in Ottawa, which is used to replace service on the O-Train Line 1. (CTV News Ottawa) An R1 bus in Ottawa, which is used to replace service on the O-Train Line 1. (CTV News Ottawa)
Share

East-end LRT riders had to board R1 buses early Saturday morning because of a power connection issue linked to Stage 2 work, OC Transpo said.

Trains were not available between St. Laurent and Blair stations at the start of service Saturday morning for what OC Transpo initially called a "track issue."

In a brief thread on X, the transit service said the delay in getting trains running in the east end was related to connecting Blair Station to the Stage 2 east extension.

"As part of the ongoing work on Stage 2, we are connecting the tracks at Blair with the new extension. This requires power to be shut off in this area. Due to a technical issue, power was not able to be restore (sic) in time for this morning's service start," OC Transpo said.

R1 buses were implemented in the east end of the Confederation Line to start the service day at 6 a.m. Full service was restored by 6:45 a.m.

OC Transpo announced last week that installation of 12 kilometres of tracks from Blair station east to Orléans was complete. Work has now shifted to installing overhead wires, signalling and communications equipment.

The eastern extension of Line 1 is slated to be complete in early 2025.

CTVNews.ca Top Stories

opinion

opinion How to use your credit card as a powerful wealth-building tool

Irresponsibly using a credit card can land you in financial trouble, but personal finance columnist Christopher Liew says when used properly, it can be a powerful wealth-building tool that can help grow your credit profile and create new opportunities.

Stay Connected