OC Transpo must hit three milestones before O-Train service resumes on Monday
The return-to-service for the O-Train Monday morning is dependent on OC Transpo reaching three milestones, including analyzing the final report from the French manufacturer on the inspection and investigation into the problem wheel hub.
And when O-Train service does resume, there will be eight single-car trains running along the 13 km route for the foreseeable future to "control the kilometres" on the vehicles, OC Transpo's boss says.
Transit Services general manager Renee Amilcar and officials from Rideau Transit Group and Rideau Transit Maintenance provided an update on the return-to-service plan Thursday afternoon, 11 days after the O-Train shutdown after a problem was discovered on an axle-bearing on one LRT vehicle during a routine inspection.
Amilcar says to resume service safely on Monday, the three milestones required are:
- Inspection of all LRT vehicles. Inspections of 44 vehicles were completed on July 23, with six vehicles undergoing additional investigations
- Final safety note from Rideau Transit Group outlining the parameters of the new containment plan for the safe operations of Line 1. A draft version of the safety note was delivered this week.
- Texelis report based on the disassembly and analysis of the out of tolerance hub. OC Transpo/RTG expect the report on Friday
"If all milestones are not met, we will not resume Line 1 service because safety is paramount," Amilcar said.
Amilcar adds that based on the findings of the report from the axle manufacturer on Friday, "We will able to confirm if there are any actionable requirements for safe operations and the timing to begin rail service."
OC Transpo and Rideau Transit Group announced Wednesday that all leading and trailing wheel hub assemblies and axles will be replaced on O-Train vehicles every 60,000 km as part of a new inspection and replacement regime.
O-Train and Rideau Transit Group will be conducting trial running along the O-Train line on Saturday and Sunday to prepare for the expected return-to-service on Monday.
Amilcar says other preparations include:
- Reviewing all stations to ensure they are clean and ready to open
- Verifying the stations and tracks are ready for operation
- Ensuring all the customer signage and announcement systems are working
- Reviewing and preparing new wayfinding signage and communications materials to assist customers in navigating the stations and R1 stop locations
- Preparing red-vested outreach: Transit Supervisors and Rail Operations staff will be at key stations along Line 1 to support customers
The O-Train was abruptly shut down on Monday, July 17 after an axle bearing issue was discovered on one train during a routine inspection. City officials said all 45 trains would need to be inspected as part of the root cause investigation into the issue before LRT service resumes.
Eight single-car trains for the foreseeable future
When O-Train service resumes, it will be running with eight, single-car LRT vehicles for the foreseeable future.
Amilcar says they will continue to run single-car trains to save kilometres ahead of the return to work and school in September.
"When Alstom will be able to give us more vehicles, we'll do a permutation with those eight trains to maintain," Amilcar said.
"We'll have to play with the trains to be able to control the kilometres because we don't want to give a service today and in one month stop everything because we have to inspect them or we have to change axles. For now, we guarantee eight trains and before we can increment that number we'll keep R1 service in place."
OC Transpo and Rideau Transit Maintenance had been operating 11 double-car trains along the O-Train line through the summer.
Amilcar also addressed criticism of the return-to-service plan with single-car trains.
"We should take a moment to recognize that our LRT system was designed to be adaptable and flexible," Amilcar said.
"We are using this design to be proactive and respond to changing conditions."
Sutcliffe "hopeful" LRT fixes will address root causes
In a statement on Twitter, Mayor Mark Sutcliffe thanked residents for their patience during the O-Train shutdown.
"I want to emphasize that I don't expect residents to have confidence in the system until service is restored, and the chronic and persistent issues we've experienced have been permanently addressed," Sutcliffe said on Thursday.
Sutcliffe says he's "hopeful and encouraged" the city and OC Transpo are "finally starting to get to the root causes" of the issues with the O-Train.
"We have been working hard to do things differently to proactively communicate with residents on the ongoing LRT work," Sutcliffe said.
"And we are focused on your safety and following the recommendations of the inquiry. We are also working collaboratively with RTG and the consortium. There’s a high level of communication with the public, and we are working toward not just temporary fixes but advancing the permanent solutions that will deliver the light rail service Ottawa residents expect and deserve."
CTVNews.ca Top Stories
Stamp prices rise for the third time in five years amid financial woes for Canada Post
Canada Post is increasing stamp prices for the third time since 2019, a move the Crown corporation says is a "reality" of its sales-based revenue structure.
BREAKING Winnipeg man admits to killing four women, claims he's not criminally responsible
Defence lawyers for Jeremy Skibicki have told the court the accused unlawfully caused the death of four women, but argue he is not criminally responsible due to mental disorder.
WATCH Avian flu: Risk to humans grows as outbreaks spread, warns expert
H5N1 or avian flu is decimating wildlife around the world and is now spreading among cattle in the United States, sparking concerns about 'pandemic potential' for humans. Now a health expert is urging Canada to scale up surveillance north of the border.
Italy's white-collar mafia is making a business killing
Italy's mafia rarely dirties its hands with blood these days. Extortion rackets have gone out of fashion and murders are largely frowned upon by the godfathers.
The story of how a B.C. man found his birth mother
After his adopted parents died, Dave Rogers set out to learn more about his birth mother. DNA results and a little help from friendly strangers would put him on a path to a small town in England.
Trump fined US$1,000 for gag order violation in hush money case as judge warns of possible jail time
The judge presiding over Donald Trump's hush money trial fined him US$1,000 on Monday for violating his gag order once again and sternly warned the former president that additional violations could result in jail time.
An El Nino-less summer is coming. Here's what that could mean for Canada
As Canadians brace themselves for summer temperatures, forecasters say a weakening El Nino cycle doesn’t mean relief from the heat.
Holocaust researchers use AI to search for unnamed victims
Researchers in Israel are turning to artificial intelligence to comb through piles of records to try to identify hundreds of thousands of Jewish people killed in the Holocaust whose names are missing from official memorials.
Russia warns Britain and plans nuclear drills over the West's possible deepening role in Ukraine
Russia plans to hold drills simulating the use of battlefield nuclear weapons, the Defense Ministry announced Monday, days after the Kremlin reacted angrily to comments by senior Western officials about the war in Ukraine and Moscow warned that tensions with the West are deepening.