OC Transpo gives the green light for full O-Train service to resume on Monday
O-Train service will resume on the full 12.5 km light-rail transit system on Monday, 28 days after the service was shut down after a bearing issue was discovered on one train.
Interim City Manager Wendy Stephanson signed off on the launch of full service between Blair and Tunney's Pasture stations, based on a recommendation from OC Transpo staff and Transportation Resource Associates following a review of RTG's documentation to confirm the requirements for the restart of Line 1 have been met.
OC Transpo and Rideau Transit Group spent the weekend conducting a trial running of trains through the east end of the rail line and verifying all the requirements have been met to resume full service.
"As previously mentioned, Rideau Transit Group (RTG) completed repositioning of the restraining rails at 16 locations to fulfill the last requirement of the Safety Note from RTG and Alstom," Transit Services general manager Renee Amilcar said in a memo Sunday evening.
"Testing was successfully conducted over the weekend to confirm the work and the system’s readiness to safely welcome customers."
There will be single-car service on the full LRT line between Blair and Tunney's Pasture stations for the month of August, as OC Transpo says it works to meet the new requirements for service and adjusts to passenger volumes.
R1 replacement bus service and R1 Express will continue to run on Monday. Amilcar says additional information about R1 service going forward will be announced on Monday.
Partial LRT service resumed on the western section of the LRT system last Tuesday, with trains running between Tunney's Pasture and uOttawa stations.
CTVNewsOttawa.ca looks at what you need to know about the return of O-Train service on Monday.
O-Train service
OC Transpo will provide single-car service on the LRT line for the month of August.
- Weekday morning peak period: 11 single-car trains will provide service at stations every five minutes
- Weekday afternoon peak period: 13 single-car trains will provide service at stations every four minutes
- Weekday non-peak periods and evenings: Nine single-car trains providing service at stations every six minutes
- Weekend service: Nine single-car trains providing service every six minutes
R1 replacement bus service
OC Transpo will continue to run R1 replacement bus service on Monday between Blair and Tunney's Pasture stations.
In downtown Ottawa, R1 bus service will use Albert and Slater streets downtown.
- Westbound R1 buses will run on Albert St. with stops at Bank and Kent
- Eastbound R1 buses will run on Slater St. with stops at Kent and O’Connor
R1 Express
The R1 Express service between Blair Station and downtown Ottawa will operate on Monday.
The route is identified as "R1 Lyon Express" and "R1 Blair Express" on the bus display. Buses will run approximately every 15 minutes, according to OC Transpo.
"R1 Lyon Express"
- The R1 Lyon Express will run westbound from 6:30 a.m. to 8:30 a.m.
- Bus service will operate from Blair Station to downtown, with stops on the Mackenize King Bridge and on Albert Street at Bank and Kent
"R1 Blair Express"
- The R1 Blair Express will run eastbound from 3 p.m. to 6 p.m.
- Bus service will operate from downtown to Blair Station with stops on Slater Street at Bank and Kent and at the Mackenize King Bridge
Maintenance work
As O-Train service returns to the full LRT line, Rideau Transit Group will continue the replacement of the wheel hub assemblies. As part of the new requirement in the Safety Note, all leading and trailing wheel hub assemblies and axles will be replaced on O-Train vehicles every 60,000 km.
As of Sunday, the wheel hub assemblies have been replaced on 28 of 44 trains.
Rideau Transit Group has also repositioned the restraining rails at eight locations along the track to ensure there is no contact between the rail and the wheel hub.
What's next
The Transit Commission and the city's Light-Rail Transit Subcommittee will receive several reports over the next two months about LRT service in Ottawa.
- Aug. 29 – LRT Subcommittee will receive an update on construction on Stage 2 of the light-rail transit system, including testing on the north-south line from Bayview Station to Riverside South
- Sept. 14 – Transit Commission will receive an update on the O-Train return-to-service
- Sept. 29 – LRT Subcommittee will receive a "deep dive" on the Trillium Line, according to city staff. There will also be an update on the city's response to the recommendations from the public inquiry into Ottawa's LRT system
- Oct. 12 – Transit Commission will receive a report on the root cause analysis on the axle-bearing issue and a report "outlining LRT incidents related to freezing rain, lightning strikes and other issues."
CTVNews.ca Top Stories
India's foreign minister reacts to murder charges, claims Canada welcomes criminals
India's Foreign Affairs Minister accused Canada of welcoming criminals from his country in response to the RCMP's recent arrests in a homicide that has roiled tensions between the two countries.
15-year-old boy stabbed in Ottawa on Thursday dies
A 15-year old boy who was critically injured after a stabbing in Nepean on Thursday has died of his injuries, Ottawa's English public school board said Sunday.
Dash cam catches moment suspected drunk driver hits parked car, sends it careening into North Shore flower shop
Police say it’s fortunate no one was injured or killed in a collision at North Vancouver’s Park and Tilford shopping centre Saturday evening that sent one vehicle careening into a flower shop and another into a set of concrete barriers outside a Winners store.
'A tiny city:' Pro-Palestinian campus protesters organize for another week
Pro-Palestinian activists have set up tents at universities in Toronto, Ottawa, Vancouver and Montreal, following a wave of similar protests at campuses in the United States linked to the Israel-Hamas war.
Lawsuit against Meta asks if Facebook users have right to control their feeds using external tools
Do social media users have the right to control what they see — or don't see — on their feeds?
Princess Anne lays wreath at Battle of Atlantic ceremony; honours late Queen
Princess Anne saluted Canadian veterans and current forces members and honoured her late mother during separate ceremonies Sunday in Victoria as she wrapped up a three-day British Columbia West Coast royal visit.
El Nino weakening doesn't mean cooler temperatures this summer, forecasters say
As Canadians brace themselves for summer temperatures, forecasters say a weakening El Nino cycle doesn’t mean relief from the heat.
As storms moves across Texas, 1 child dies after being swept away in floodwaters
A child in Texas died Sunday after being swept away in floodwaters as storms swept across the state.
Nylander defends Leafs' core after playoff exit, Toronto again picks up the pieces
The Maple Leafs battled back from a 3-1 series deficit against the Boston Bruins with consecutive 2-1 victories - including one that required extra time - in their first-round playoff series to push the club's Original Six rival to the limit before suffering a devastating Game 7 overtime loss.