Here are the Ottawa LRT inquiry's key recommendations
The Ottawa Light Rail Transit Inquiry makes 103 recommendations in the final report to fix the problems with the Confederation Line and "ensure they don't reoccur" on other major infrastructure projects.
The recommendations cover several different areas: planning complex infrastructure, preparing project estimates and budgets, selecting a project delivery model, risk reduction during procurement, safety requirements, ensuring a skilled workforce, transparency between operations and maintenance, accuracy and transparency, oversight during public service, adopting a partnership approach between owner, operator and maintainer, creating an effective contract scheme, efficient and effective warranty service, and maintenance during public service.
Commissioner William Hourigan also makes recommendations on how the city of Ottawa, Rideau Transit Group/Rideau Transit Maintenance, Alstom and other parties can address breakdowns and derailments, and how to run a system in a manner "that aligns with the best interest of transit users" and Ottawa residents.
"There is reason for optimism, as the parties have begun working together more co-operatively and the reliability of the system is showing some signs of improvement. This improvement demonstrates that, over time, structural problems can be resolved through good faith, communication, and co-operation," Hourigan writes.
"However, until such time as the private and public entities involved in the OLRT1 project understand that their first obligation is to the public, there is reason to be concerned that the project will continue to suffer problems."
Here is a look at the Ottawa Light Rail Transit Inquiry recommendations for the Confederation Line
Recommendations for the OLRT1
- Work undertaken to strengthen the City’s oversight framework should continue, including assessing OC Transpo’s oversight and monitoring programs and making any improvements identified to ensure safety and reliability of the system.
- Following incidents on the system, OLRT1 parties should continue to hold debrief meetings with all stakeholders present, in order to identify lessons learned and make improvements going forward.
- A partnership approach should be adopted during the operations and maintenance phase and to address issues that arise on the system.
- Outstanding payment disputes between the City and RTG should be resolved at the earliest opportunity, in particular related to the City’s approach to issuing and classifying work orders, and the City’s administration of the payment mechanism
- If RTG continues to be responsible for maintenance during the remainder of the maintenance term, RTG and the City, as well as RTM and Alstom Maintenance, should make efforts to repair their relationships and work together better for the greater good of the OLRT1 project.
Future Assessments and Preventive Maintenance
- If not yet complete, an engineering assessment of the appropriate rail neutral temperature for the OLRT1 should be completed, and the rail neutral temperature adjusted accordingly, so that the track buckling issues can be mitigated for the long term.
- Alstom should continue its preventive maintenance of the line inductors, including checking them before and after every winter for any buildup of contaminants, and cleaning them as required.
- Alstom should continue its regular inspections of the overhead catenary system to clean the parafils as required, or repair/replace them as necessary.
- The City, RTG and its subcontractors, and Alstom must follow through on the outstanding investigations regarding the root cause of the August 8, 2021 derailment, act on the findings, and ensure that any root cause of this derailment is addressed.
- A permanent solution to the wheel/rail interface issues needs to be identified and implemented in a timely manner. This solution may involve using a different type of wheel, replacing the track or part of the track, additional track reprofiling, enhancing the axle design to withstand the forces coming from the track, or even modifying the track alignment to address the issue of sharp curves. A wheel/rail interaction study should be undertaken to determine the appropriate solution(s). All parties should work co-operatively to implement the solution(s).
- Transportation Resource Associates or another independent third-party expert should continue to monitor safety issues and remedial actions undertaken by the parties to ensure the continued safe operation of the OLRT1 system, pending a final resolution of the issues relating to the wheel/rail interface and the first derailment. This independent safety expert should report directly to Council or to the Transit Commission.
- The city and RTG should continue implementing current remedial measures intended to ensure the safe and reliable operation of the system following the Aug. 8, 2021 derailment, including: Reducing rail corrugation through maintenance, increasing track lubrication (greasing), lowering speeds in some places, and modifying the wheel profile to better "sustain the transversal forces" coming from the track
- RTM should implement the recommendation first made in the Track Safety Justification Report and the Operational Restrictions Document, and establish a wheel/rail working group to optimize the wheel and rail profiles, improve maintenance practices, monitor the wheel/rail interface, and minimize the impacts on the rail and vehicle components.
- The operating profile should be adjusted as necessary to ensure the safety and reliability of the OLRT1 system by reducing stress on the vehicle components and avoiding excessive wear. Consideration should be given to reducing vehicle speeds, particularly along curves and to account for different climatic conditions.
- Alstom should follow through with its plans to replace the spline axles on the LRVs following the problems with excessive wear to the splines that were identified in its presentation dated June 30, 2021.
- The parties should consider the use of a detection system as a potential remedial option for overheated roller bearings.
CTVNews.ca Top Stories
Canadian gov't proposes new foreign influence registry as part of wide-spanning new bill
Prime Minister Justin Trudeau's government is proposing a suite of new measures and law changes aimed at countering foreign interference in Canada, amid extensive scrutiny over past meddling attempts and an ever-evolving threat landscape.
Boeing Starliner capsule's first crewed test flight postponed
The long-awaited first crewed test flight of Boeing's new Starliner space capsule was called off for at least 24 hours over a technical issue that launch teams were unable to resolve in time for the planned Monday night lift-off.
Teacher charged in historical sexual assault of Calgary teenage girl
Calgary police have charged a teacher with the alleged sexual assault of a teenage girl more than 20 years ago.
Winnipeg man admits to killing four women, argues he's not criminally responsible
Defence lawyers of Jeremy Skibicki have admitted in court the accused killed four Indigenous women, but argues he is not criminally responsible for the deaths by way of mental disorder – this latest development has triggered a judge-alone trial rather than a jury trial.
Man banned from owning animals after fatal Calgary dog attack
The owner of three Calgary dogs that got loose and mauled a woman to death in 2022 has been ordered to pay a $15,000 fine within one year and banned from owning any animal for 15 years.
East-end Ottawa family dealing with massive rat infestation
Residents in Ottawa’s Elmridge Gardens complex are dealing with a rat infestation that just won’t go away. Now, after doing everything they can to try to fix the issue, they are pleading with the city to step in and help.
Mediterranean staple may lower your risk of death from dementia, study finds
A daily spoonful of olive oil could lower your risk of dying from dementia, according to a new study by Harvard scientists.
An El Nino-less summer is coming. Here's what that could mean for Canada
As Canadians brace themselves for summer temperatures, forecasters say a weakening El Nino cycle doesn’t mean relief from the heat.
Newfoundland and Labrador latest province to tighten rules on Airbnbs
Newfoundland and Labrador is the latest jurisdiction to bring in stricter rules for short-term rentals, with a coming set of regulations that will force operators to register with the provincial government.