Construction on Ottawa's north-south rail line hits another delay
Construction on Ottawa's north-south rail line has hit a new delay, with the handover of the Trillium Line to the city of Ottawa now not expected until at least early November.
Councillors received an update on construction for Stage 2 of the rail system in Ottawa on Wednesday, including the north-south line from Bayview Station to Riverside South, with a spur to the Ottawa International Airport.
Michael Morgan, the city's director of rail construction, says based on the current review of all inputs including an agreement on the training requirements, "the updated working timeline for the project handover is before the end of the year."
Morgan says, "There remains some risk and uncertainty in the completion" of the remaining work.
"Trackwork is largely complete; however, progress on signal testing is advancing slowly and requires additional time which is pushing the overall handover timeline to no sooner than early November," Morgan said.
"Staff also continue to monitor progress at stations noting that all stations still require occupancy permits and all stations require TSSA approvals for elevators."
In May, Morgan said the timeline was to aim for trial running to begin in the third week of September, with the handover planned for the first or second week of October.
The achievement of the handover milestone is contingent upon four things, according to Morgan.
- Successful completion of signal testing
- Successful completion of system wide commissioning including stations
- Transport Canada approvals
- Training completion
Morgan says subsequent to project handover, the city will make an assessment on the timing for the launch of public service.
The Trillium Line was originally scheduled to open in August 2022, and was then delayed until September 2023.
Following the completion of construction and the testing and commissioning program, TransitNEXT will conduct a three-week trial period to "validate that all aspects of the system and maintenance activities perform as expected," Morgan said.
"Following the successful completion of Trial Running as well as completion of all PA requirements, Substantial Completion will be achieved," Morgan writes.
"The system will then be available for OC Transpo to complete any remaining operational readiness activities before determining a final opening date to the public. The duration of this final process for validation of system readiness is still to be determined."
Confederation Line
Construction on the Confederation Line continues to slowly move along.
Morgan says the eastern extension to Trim Road is currently seven weeks behind schedule, with construction expected to be completed in the first quarter of 2025.
The western extension from Tunney's Pasture Station to Moodie and Algonquin stations is up to 17 months behind schedule, with construction now expected to end in late 2026.
"Specific elements such as the Moodie Light Maintenance and Storage Facility (LMSF) and Lincoln Fields Station are progressing well," Morgan writes.
"Production rates and accumulated delays on the Cut and Cover Tunnel along the Sir John A. Macdonald Parkway and Byron Linear Park are pushing the overall project completion date to late 2026."
CTVNews.ca Top Stories
India's foreign minister reacts to murder charges, claims Canada welcomes criminals
India's Foreign Affairs Minister accused Canada of welcoming criminals from his country in response to the RCMP's recent arrests in a homicide that has roiled tensions between the two countries.
15-year-old boy stabbed in Ottawa on Thursday dies
A 15-year old boy who was critically injured after a stabbing in Nepean on Thursday has died of his injuries, Ottawa's English public school board said Sunday.
Dash cam catches moment suspected drunk driver hits parked car, sends it careening into North Shore flower shop
Police say it’s fortunate no one was injured or killed in a collision at North Vancouver’s Park and Tilford shopping centre Saturday evening that sent one vehicle careening into a flower shop and another into a set of concrete barriers outside a Winners store.
Actor Bernard Hill, of 'Titanic' and 'Lord of the Rings,' has died at 79
Actor Bernard Hill, who delivered a rousing cry before leading his people into battle in 'The Lord of the Rings: The Return of the King' and went down with the ship as the captain in 'Titanic,' has died.
'A tiny city:' Pro-Palestinian campus protesters organize for another week
Pro-Palestinian activists have set up tents at universities in Toronto, Ottawa, Vancouver and Montreal, following a wave of similar protests at campuses in the United States linked to the Israel-Hamas war.
Lawsuit against Meta asks if Facebook users have right to control their feeds using external tools
Do social media users have the right to control what they see — or don't see — on their feeds?
A Holocaust survivor will mark that history differently after the horrors of Oct. 7
This year's Holocaust Remembrance Day, which begins on Sunday evening in Israel, carries a heavier weight than usual for many Jews around the world.
Princess Anne lays wreath at Battle of Atlantic ceremony; honours late Queen
Princess Anne saluted Canadian veterans and current forces members and honoured her late mother during separate ceremonies Sunday in Victoria as she wrapped up a three-day British Columbia West Coast royal visit.
El Nino weakening doesn't mean cooler temperatures this summer, forecasters say
As Canadians brace themselves for summer temperatures, forecasters say a weakening El Nino cycle doesn’t mean relief from the heat.