LRT construction delays keeping footbridge near Carleton campus incomplete
A much-anticipated footbridge connecting Carleton University to Vincent Massey Park has been sitting unused for nearly two years, and the delay has everything to do with light rail construction.
Ian Marsland, a cyclist eager to use the bridge, says the link between the university and Vincent Massey's vast network of recreational pathways on the other side of the Rideau River is not only a much-needed gateway but also reduces travel time to other destinations like the RA Centre and Billings Bridge.
"It's going to be fantastic," he says. "It crosses the river in a place where it's very hard to cross the river right now. It's either up to Hog's Back or over to Bank Street, so this is good for the campus and the park."
The massive one-piece steel structure footbridge was originally installed in July 2022 and, at the time, several city councillors, including Riley Brockington, expected an opening within four months. That did not happen.
"We learn now that the contract is tied with the opening of the LRT Line 2," says Brockington.
The bridge and its installation is part of the original Stage-two LRT proposal.
- Sign up now for daily CTV News Ottawa newsletters
- The information you need to know, sent directly to you: Download the CTV News App
"So as long as Line 2 is postponed, this bridge, per contract, does not does not have to open," Brockington says. "My argument is there's so little work left, basically electrical connections and some of the top bridge work weatherproofing."
Brockington wants the footbridge opened by this summer. City staff note that in order to complete work on the bridge, sustained above-zero temperatures will be needed.
CTVNews.ca Top Stories
Hackers release corporate data stolen from London Drugs
Retailer London Drugs says cybercriminals who stole files from its corporate head office last month have released some of the data after it refused to pay a ransom.
Toronto man falls off his chair after seeing $70M Lotto Max win in his bank account
A Toronto man who won $70 million in a recent Lotto Max draw literally fell off his chair when he saw the funds in his bank account.
Montreal-area high school students protest 'sexist' dress code
Approximately 50 Montreal-area students — the vast majority of them female — were suspended Wednesday after their school deemed the shorts they were wearing were too short. On Thursday, several students staged a walk-out to protest what they believe is a "sexist" dress code that unfairly targets girls.
McDavid scores in 2OT to lift Oilers over Stars in West Final opener
Connor McDavid tipped Evan Bouchard's shot from the boards past Dallas Stars goalie Jake Oettinger 32 seconds into the second overtime to give the Edmonton Oilers a 3-2 win in Game 1 of the Western Conference Final..
'Looking over our shoulders': A killing looms large in a little B.C. town
Something shifted in the pretty little village of Lumby, B.C., after Tatjana Stefanski vanished. It used to be the sort of place where parents let their kids roam free or play in the local creek, but everything has changed.
What is 'slapped cheek disease' and should parents be concerned?
Despite its rough name, experts say most cases of 'slapped cheek disease' are mild and not a cause for concern.
American Airlines retreats after blaming a 9-year-old for not seeing a hidden camera in a lavatory
American Airlines has distanced itself from a court filing in which the carrier said a nine-year-old girl should have noticed there was a camera taped to the seat of an airplane lavatory.
Unknown Newfoundland soldier from the First World War heads back home from France after 100 years
Canadian soldiers and government officials arrived in northeastern France this week for a historic mission: returning an unknown Newfoundland soldier back home.
Calgary Philharmonic takes action following investigation into 'deeply troubling' comments by 2 musicians
The Calgary Philharmonic has confirmed its taking action after controversial online comments made by two members of the orchestra.