Full O-Train service could be shut down for three weeks after LRT train derailment: RTM
Rideau Transit Maintenance warns it could be three weeks before full service resumes on the Confederation Line after an LRT car derailed this weekend, causing significant damage to the transit infrastructure.
A set of wheels on a train left the tracks early Sunday afternoon just west of Tremblay Station. There were 12 passengers and an LRT driver on board at the time but nobody was hurt.
The derailment—the second on the line in six weeks—brought the entire LRT service to a halt Sunday and Monday. R1 bus service is replacing the LRT from Tunney's Pasture to Blair stations.
A device that is used to put sand on the rails in the winter could be behind the derailment on Ottawa's $2.1 billion Confederation Line LRT, the city’s transit chief said Monday.
OC Transpo general manager John Manconi told the transit commission that very preliminary information suggests that this latest derailment does not appear to be related to the axle bearing problem that derailed a train in August, but rather to a sanding device on the underside of the train is used in winter to cut down on icing and add traction.
"The bracket that holds that unit could have become dislodged and could have caused the derailment," Manconi said, while stressing that these are very early findings that have not been certified and are not the Transportation Safety Board's findings.
"They are very, very early in the investigation phase but I thought it would be prudent (to share) because I'm aware that there's concerns about the overall safety and reliability of the system," Manconi said.
"The TSB is out there assessing everything, they're controlling the site and the vehicle. This is not their finding. This is the collective discussion that's been occurred by the many safety officials and rail experts that are out there, looking at what occurred."
OUT OF SERVICE
Speaking with reporters after the transit commission meeting, the chief executive officer of Rideau Transit Maintenance said their inspection showed there is significant damage to the track and infrastructure.
“We have realized attending the scene today with TSB and the city that there’s a lot more infrastructure damage than we originally thought. I think that may be on the critical path is our ability to get in there and repair all the damage to the ties, to the clips, to the switch machine. There’s a lot of work to be done,” said Mario Guerra.
“I think we’re probably looking, to get the entire system back up and running, that’s assuming that we can satisfy everyone that it’s safe to resume service I would say three weeks probably. We could look at running some partial service.”
Guerra said partial O-Train service could return west of the derailment site as the inspection and repairs continue. Contractors will be on the scene Tuesday to provide a full assessment on the damage and what will be needed to fix the train.
“It will probably take us three weeks to make all the repairs to the infrastructure. We may run a partial service at some point. For full service to resume, I would say it will be a little while before we get the infrastructure repaired.”
Affected train had undergone axle repairs: Charter
Director of Transit Operations Troy Charter told the transit commission Monday morning that the car involved in Sunday's derailment had recently returned to service following axle repairs, adding that the preliminary information suggests the cause of Sunday's derailment is not the same as the cause of the Aug. 8 derailment.
Rideau Transit Group CEO Nicolas Truchon told transit commission that the bracket holding the sander device in place would need to be removed and reinstalled during the axle repair.
"The bolts are torqued and there are torque marks that are put on the bolts that act as a visual for inspections to ensure that the bolts have not come loose," he said.
Independent review
The TSB said in a release Monday that it has deployed an investigator to the scene to assess the incident. So far, a formal investigation has not yet been launched.
Manconi said he is recommending an independent review of Rideau Transit Maintenance's (RTM) plan for a return to service before the Confederation Line reopens to customers.
"I've instructed our chief safety officer to include in the order to RTM that before we can restore service for this incident, Sam Berrada, your independent rail regulatory officer, will be recommending to Mr. Kanellakos (Ottawa's City Manager) an independent safety officer review the return-to-service plan that RTM is proposing," Manconi said.
'We bought a lemon': Councillor calls for end to contract with Rideau Transit Group
Speaking on CTV News at Noon, Coun. Diane Deans said Ottawa's transit system is "in crisis" and she's calling for the city to sever its ties with Rideau Transit Group, the consortium that built and now maintains the line as Rideau Transit Maintenance.
"My number one question is, 'How do we get rid of Rideau Transit Maintenance Group?' We have a 30-year contract. They're clearly not maintaining the system to the standards we need. It's time for us to move on and I want to know how we do that," Deans said.
Early last year, following the first months of service, which saw several problems with doors, brakes, onboard computer systems, overhead catenary wires and others, other councillors--including transit commission chair Allan Hubley--had asked similar questions. A report prepared for the city's finance and economic development committee in March 2020 said calculating the cost of terminating the contract with RTG was incredibly complex.
"That is due to the fact that the cost to the City of termination must necessarily include not only those costs directly associated with termination, but also any costs arising from setting up an alternate service provider," the report said.
Deans called the system "substandard" and said citizens sould not have to endure 30 years of poor performance.
"This is a substandard system. We bought a lemon and we need to get rid of this whole maintenance contract," Deans said. "We need to bring in new rail experts that tell us what it will take financially a]nd from a service perspective to put a system in place that is going to serve us well for the next 30 years. Continuing to make excuses for a substandard system is just not going to cut it."
Coun. Shawn Menard asked Hubley whether he would resign as chair of the transit commission. Hubley said he would not.
CTVNews.ca Top Stories
Solar storm puts on brilliant light show across the globe, but no serious problems reported
A powerful solar storm put on an amazing skyward light show across the globe overnight but has caused what appeared to be only minor disruptions to the electric power grid, communications and satellite positioning systems.
'It was violent': Police tear down U of A pro-Palestinian encampment Saturday morning
Multiple people at the protest camp torn down at the University of Alberta campus Saturday say police's actions against protesters were "violent" and "disproportionate."
'I am angry': Alberta farmers will continue fight over world class motorsport resort
The rolling hills leading to the hamlet of Rosebud are dotted with sprawling farms and cattle pastures -- and a sign sporting a simple message: No Race Track.
'My family doctor just fired me': Ontario patients frustrated with de-rostering
Dozens of Ontarians are expressing frustration in the province’s health-care system after their family doctors either dropped them as patients or threatened to after they sought urgent care elsewhere.
Canada Post cracks down on Nunavut loophole to get free Amazon Prime shipping
Amazon's paid subscription service provides free delivery for online shopping across Canada except for remote locations, the company said in an email. While customers in Iqaluit qualify for the offer, all other communities in Nunavut are excluded.
Potentially toxic chemicals hide in our drinking water and countless household objects, and they're not going anywhere
For decades, North Bay, Ontario's water supply has harboured chemicals associated with liver and developmental issues, cancer and complications with pregnancy. It's far from the only city with that problem.
Suspect sought after fatal slashing in downtown Toronto
Police are searching for a suspect in a homicide investigation after a man was slashed in downtown Toronto on Sunday.
U.S. aims to stay ahead of China in using AI to fly fighter jets, navigate without GPS and more
When two U.S. fighter jets recently faced off in a dogfight in California, only one was piloted by a human.
'Increased fire activity' expected for Fort Nelson, B.C., blaze
A wildfire near Fort Nelson, B.C., that forced thousands to flee their homes grew almost 800 hectares overnight Saturday, according to officials.