Construction on Ottawa's north-south rail line hits another delay
Construction on Ottawa's north-south rail line has hit a new delay, with the handover of the Trillium Line to the city of Ottawa now not expected until at least early November.
Councillors received an update on construction for Stage 2 of the rail system in Ottawa on Wednesday, including the north-south line from Bayview Station to Riverside South, with a spur to the Ottawa International Airport.
Michael Morgan, the city's director of rail construction, says based on the current review of all inputs including an agreement on the training requirements, "the updated working timeline for the project handover is before the end of the year."
Morgan says, "There remains some risk and uncertainty in the completion" of the remaining work.
"Trackwork is largely complete; however, progress on signal testing is advancing slowly and requires additional time which is pushing the overall handover timeline to no sooner than early November," Morgan said.
"Staff also continue to monitor progress at stations noting that all stations still require occupancy permits and all stations require TSSA approvals for elevators."
In May, Morgan said the timeline was to aim for trial running to begin in the third week of September, with the handover planned for the first or second week of October.
The achievement of the handover milestone is contingent upon four things, according to Morgan.
- Successful completion of signal testing
- Successful completion of system wide commissioning including stations
- Transport Canada approvals
- Training completion
Morgan says subsequent to project handover, the city will make an assessment on the timing for the launch of public service.
The Trillium Line was originally scheduled to open in August 2022, and was then delayed until September 2023.
Following the completion of construction and the testing and commissioning program, TransitNEXT will conduct a three-week trial period to "validate that all aspects of the system and maintenance activities perform as expected," Morgan said.
"Following the successful completion of Trial Running as well as completion of all PA requirements, Substantial Completion will be achieved," Morgan writes.
"The system will then be available for OC Transpo to complete any remaining operational readiness activities before determining a final opening date to the public. The duration of this final process for validation of system readiness is still to be determined."
Confederation Line
Construction on the Confederation Line continues to slowly move along.
Morgan says the eastern extension to Trim Road is currently seven weeks behind schedule, with construction expected to be completed in the first quarter of 2025.
The western extension from Tunney's Pasture Station to Moodie and Algonquin stations is up to 17 months behind schedule, with construction now expected to end in late 2026.
"Specific elements such as the Moodie Light Maintenance and Storage Facility (LMSF) and Lincoln Fields Station are progressing well," Morgan writes.
"Production rates and accumulated delays on the Cut and Cover Tunnel along the Sir John A. Macdonald Parkway and Byron Linear Park are pushing the overall project completion date to late 2026."
CTVNews.ca Top Stories
'A beautiful soul': Funeral held for baby boy killed in wrong-way crash on Highway 401
A funeral was held on Wednesday for a three-month-old boy who died after being involved in a wrong-way crash on Highway 401 in Whitby last week.
'Sophisticated' cyberattacks detected on B.C. government networks, premier says
There has been a "sophisticated" cybersecurity breach detected on B.C. government networks, Premier David Eby confirmed Wednesday evening.
Police handcuff man trying to enter Drake's Toronto mansion
Toronto police say a man was taken into custody outside Drake's Bridle Path mansion Wednesday afternoon after he tried to gain access to the residence.
Biden says he will stop sending bombs and artillery shells to Israel if they launch major invasion of Rafah
U.S. President Joe Biden said for the first time Wednesday he would halt shipments of American weapons to Israel, which he acknowledged have been used to kill civilians in Gaza, if Prime Minister Benjamin Netanyahu orders a major invasion of the city of Rafah.
Rookie goalie Arturs Silovs to start for Canucks in Game 1 vs. Oilers
Rookie goalie Arturs Silovs will start in net for the Canucks as Vancouver kicks off a second-round series against the Edmonton Oilers Wednesday night.
Nijjar murder suspect says he had Canadian study permit in immigration firm's video
One of the Indian nationals accused of murdering British Columbia Sikh activist Hardeep Singh Nijjar says in a social media video that he received a Canadian study permit with the help of an Indian immigration consultancy.
Pfizer agrees to settle more than 10K lawsuits over Zantac cancer risk: Bloomberg News
Pfizer has agreed to settle more than 10,000 lawsuits about cancer risks related to the now discontinued heartburn drug Zantac, Bloomberg News reported on Wednesday, citing people familiar with the deal.
Quebec premier defends new museum on Quebecois nation after Indigenous criticism
Quebec Premier Francois Legault is defending his comments about a new history museum after he was accused by a prominent First Nations group of trying to erase their history.
U.S. presidential candidate RFK Jr. had a brain worm, has recovered, campaign says
Independent U.S. presidential candidate Robert F. Kennedy Jr. had a parasite in his brain more than a decade ago, but has fully recovered, his campaign said, after the New York Times reported about the ailment.