O-Train travels east of Blair Station for first time as part of LRT Stage 2 construction
The O-Train slowly travelled east of Blair Station for the first time Sunday evening, as construction continues on Stage 2 of Ottawa's light-rail transit project.
In a memo to Council Monday morning, OC Transpo acting general manager Michael Morgan said an Alstom Citadis Spirit train operated on the O-Train East extension for the "first time" from Blair Station to Montreal Station following the end of regular O-Train Line 1 service Sunday evening.
"Travelling at walking speed, the train was escorted by staff on foot to verify the interface between the train’s pantograph and the OCS while the train was in motion," Morgan said, calling it an "important milestone" on the O-Train east extension.
"Additional testing between Blair Station and Montréal Station is anticipated later this week as crews continue to test and validate the (overhead catenary system) system."
- Sign up now for our daily CTV News Ottawa newsletters
- The information you need to know, sent directly to you: Download the CTV News App
Morgan says OC Transpo was able to move a train east of Blair Station following testing activities including track commissioning, traction power substation testing and overhead catenary system testing.
"It was a very big step and the team was really excited to get it down last night," Morgan told Newstalk 580 CFRA's Ottawa at Work with guest host Graham Richardson.
"First time a train has gone past the end of Blair Station on the way to Montreal Station, so it was a pretty exciting time for the team."
As part of Stage 2 of Ottawa's LRT system, the Confederation Line will be extended 12.5 km east from Blair Station to Trim Road, with five new stations at Montreal Road, Jeanne d'Arc Boulevard, Convent Glen, Place d’Orléans and Trim Road.
"Testing of the signal and train control system is expected to start this spring, after which residents will see regular, slow speed testing of trains on the line," Morgan says.
Morgan says last night's testing was focusing on the rail infrastructure, and not the LRT vehicle itself.
"We basically have a full year of testing and then we're going to start our training program early next year ahead of going into passenger service."
A report for the light rail transit sub-committee meeting on Thursday says the overhead catenary system cable installation is complete between Blair Station and approaching Jeanne d'Arc Station, with cable installation beginning east of Jeanne d'Arc station towards Trim Station. The energization of the Traction Power Substations for Montreal and Jeanne d'Arc stations will take place early this year.
"All trackwork in the east has been completed with the continuation of deficiency correction work," the report says. "Finishing works at Montreal and Jeanne d’Arc stations continue. Mechanical and electrical work is ongoing at Convent Glen, Place d’Orléans, and Trim stations."
OC Transpo has said full revenue service on the eastern extension of the LRT system is expected to begin in late spring 2025.
"By the end of the year, we should have multiple trains going all the way to Trim Station," Morgan said Monday morning.
"I mean it's a start," said Drake Witwicki who learned of the tests Monday. He relies on the LRT, commuting from Orléans to downtown Ottawa daily. "It's a good start and they need to keep making good starts until they get to the finish. I mean that's all you can really ask for but I just don't have a lot of trust in it."
Multiple issues have surrounded the LRT since day one, leaving riders frustrated and wary of the service.
"With stage one, the system was rushed into service for political reasons and it wasn't ready and they knew it wasn't ready, so this time they're being extremely cautious," said president of advocacy group Transport Action Canada, David Jeanes.
"Stage two is the game changer in my mind," said Coun. Tim Tierney. "Stage one is the backgrounder... clearly we've had issues with stage one but stage two has been doing a terrific job plowing ahead."
More testing between Blair and Montreal stations is expected later this week. The target date for service is 2025.
"It's pretty cool, though; I've been waiting for it for awhile," said transit user Juliane Meheux. "It's going to be so much easier to get form one place to another instead of doing an hour trek to the city... I do maybe 45 minutes?"
The western extension of the Confederation Line to Algonquin College and Moodie Drive is expected to open in late 2026, 17 months behind schedule.
The new north-south Trillium Line, operating between Bayview Station and Riverside South, is expected to open this spring.
Morgan says OC Transpo and its partners are "leveraging the lessons learned" to improve the LRT system as it expands.
"It's getting better and better every day and once we're done with Stage 2, the reach and expanse of the system is going to be fabulous for the city of Ottawa."
Ottawa's light rail transit sub-committee will receive an update on the LRT construction on Thursday.
--With files from CTV News Ottawa's Jackie Perez.
CTVNews.ca Top Stories
Robert Pickton to remain in medically induced coma until later this week: police
Serial killer Robert Pickton will remain in a medically induced coma for at least the next few days following an attack in a Quebec prison Sunday, according to police spokesperson Hugues Beaulieu.
Charlie Colin, founding member of the pop-rock band Train, dies at 58
Charlie Colin, bassist and founding member of the American pop-rock band Train, best known for their early-aughts hits like 'Drops of Jupiter' and 'Meet Virginia,' has died. He was 58.
'Five feet nothing': Pickton's safety likely behind Quebec transfer, says ex-prison judge
When serial killer Robert Pickton was transferred from British Columbia's Kent Institution to a maximum security prison in Quebec about six years ago, correctional authorities gave no public explanation or confirmation at the time, citing privacy.
'I feel betrayed': Ottawa-area customers out thousands of dollars warn of bad faith contractor
A group of people from eastern Ontario and western Quebec is issuing a warning about Dennis Walker and his company Vue Windows.
Fancy pigeon outfitted in custom diaper has free rein in B.C. family home
When Chrissy Chin volunteered to take in a fancy pigeon abandoned on a park bench, she never imagined she would one day be ordering custom-made diapers for the bird – who lives in her house and has become a member of the family.
'We'll need all hands on deck': Details emerge after deadly boat crash near Kingston
Police say they have wrapped up their on-scene investigation into a deadly boat crash in eastern Ontario as details of the incident begin to emerge.
5 dead and at least 35 hurt in Iowa tornado: officials
Five people died and at least 35 were hurt as powerful tornadoes ripped through Iowa Tuesday, with one carving a path of destruction through the town of Greenfield, officials said.
WestJet planning new fare category for travellers willing to forgo carry-on bag
WestJet Airlines plans to launch a new cheaper fare category that would be available to travellers willing to fly without a carry-on bag.
Woman found dead in Lake Ontario in 2017 matches identity of missing person in Switzerland
Genetic genealogy has helped Toronto police identify a woman who was found dead in Lake Ontario in 2017.