LRT construction delays keeping footbridge near Carleton campus incomplete
A much-anticipated footbridge connecting Carleton University to Vincent Massey Park has been sitting unused for nearly two years, and the delay has everything to do with light rail construction.
Ian Marsland, a cyclist eager to use the bridge, says the link between the university and Vincent Massey's vast network of recreational pathways on the other side of the Rideau River is not only a much-needed gateway but also reduces travel time to other destinations like the RA Centre and Billings Bridge.
"It's going to be fantastic," he says. "It crosses the river in a place where it's very hard to cross the river right now. It's either up to Hog's Back or over to Bank Street, so this is good for the campus and the park."
The massive one-piece steel structure footbridge was originally installed in July 2022 and, at the time, several city councillors, including Riley Brockington, expected an opening within four months. That did not happen.
"We learn now that the contract is tied with the opening of the LRT Line 2," says Brockington.
The bridge and its installation is part of the original Stage-two LRT proposal.
- Sign up now for daily CTV News Ottawa newsletters
- The information you need to know, sent directly to you: Download the CTV News App
"So as long as Line 2 is postponed, this bridge, per contract, does not does not have to open," Brockington says. "My argument is there's so little work left, basically electrical connections and some of the top bridge work weatherproofing."
Brockington wants the footbridge opened by this summer. City staff note that in order to complete work on the bridge, sustained above-zero temperatures will be needed.
CTVNews.ca Top Stories
'I just can't believe that it took so long': Body found in wreckage 3 months after deadly fire
A man accused of arson in a January Old Strathcona apartment fire is expected to be charged with manslaughter after a body was discovered in the burned building late last month.
No proof man lied to brother about number of kittens born in litter, B.C. tribunal rules
A man was denied a $5,000 payout from his brother after a B.C. tribunal dismissed his claim disputing how many kittens were born in a litter.
Quebec police hand out hundreds of tickets to Hells Angels and other bikers before 'first run' meeting
Quebec provincial police handed out hundreds of fines to Hells Angels members and other supporting motorcycle clubs who met for their 'first run' in a small town near Sherbrooke, Que.
Explosion at train station leads to discovery of stolen car on Montreal's South Shore: police
Police are investigating after a BMW exploded in the St-Lambert Exo train station parking lot on Montreal's South Shore.
A Chinese driver is praised for helping reduce casualties in a highway collapse that killed 48
A Chinese truck driver was praised in local media Saturday for parking his vehicle across a highway and preventing more cars from tumbling down a slope after a section of the road in the country's mountainous south collapsed and killed at least 48 people.
There's progress reported in Gaza truce talks, but Israel downplays chances of ending war with Hamas
A delegation of the Palestinian militant group Hamas was in Cairo on Saturday as Egyptian state media reported "noticeable progress" in cease-fire talks with Israel, though an Israeli official downplayed the prospects for a full end to the war in Gaza.
Snakes almost on a plane: U.S. TSA discovers a bag with small snakes in passenger's pants
According to an X post by the Transportation Security Administration, officers at the Miami International Airport found the small bag of snakes hidden in a passenger's trousers on April 26 at a checkpoint.
Russia puts Ukrainian President Zelenskyy on its wanted list
Russia has put Ukrainian President Volodymyr Zelenskyy on its wanted list, Russian state media reported Saturday, citing the interior ministry’s database.
A candidate for Germany's key party was beaten up while campaigning for European elections
A candidate for Chancellor Olaf Scholz's center-left party in next month's election for the European Parliament was beaten up and seriously injured while campaigning in an eastern city, the party said Saturday.