Here's how staff will try to prevent freezing rain buildup on Ottawa's LRT
The city of Ottawa says Rideau Transit Maintenance (RTM) is exploring the use of anti-icing chemicals to prevent a repeat of this year's freezing rain-related shutdowns to the LRT.
Trains were halted for six days in early January and two days in early April because of ice buildup on the overhead wires that power the electric trains.
The freezing rain event in January was made worse when the trains that were sent to recover the first two stuck trains became stuck themselves. Staff said a moist fog rising from the Rideau River because of warmer than average temperatures at the time contributed to ice buildup on the line between uOttawa and Hurdman stations.
In a report prepared for the Oct. 12 transit commission meeting, staff say RTM will be testing an anti-ice chemical treatment this month to be prepared for the coming winter. The chemical sticks to the overhead wires and helps prevent ice from building up during freezing rain. Other transit agencies like the TTC in Toronto use this method to prevent freezing rain accretion.
Staff expect the de-icing agent will be applied to "problematic areas" such as the part of the line between Hurdman and uOttawa stations.
Trains will also be outfitted with more de-icing strips on the device that connects to the wires to scrape ice off the line. This can cause additional wear and tear, staff warn, but they will only be outfitted on the trains if freezing rain is anticipated or happening.
RTM is also planning to rent a diesel-powered rail car mover, called a "shunter" to help rescue trains that might become stuck in the event of a power outage. This is expected to be tested this month and deployed this coming winter, if necessary.
In the longer-term, RTM is also looking at adding a heat tracing cable to the contact wire on the overhead power system, but this won't be ready until at least winter of 2024/25.
CTVNews.ca Top Stories
'Looking over our shoulders': A killing looms large in a little B.C. town
Something shifted in the pretty little village of Lumby, B.C., after Tatjana Stefanski vanished. It used to be the sort of place where parents let their kids roam free or play in the local creek, but everything has changed.
Officer who arrested Scottie Scheffler is being disciplined for not having bodycam activated
The Kentucky police officer who arrested top-ranked golfer Scottie Scheffler outside the PGA Championship is receiving “corrective action” for failing to have his body-worn camera activated.
Toronto man falls off his chair after seeing $70M Lotto Max win in his bank account
A Toronto man who won $70 million in a recent Lotto Max draw literally fell off his chair when he saw the funds in his bank account – and the life-changing moment was caught on video.
Montreal-area high school students protest 'sexist' dress code
Students at Curé-Antoine-Labelle High School near Montreal are protesting after they say their school's administration started pushing what they call a 'sexist' dress code.
Air travel is expensive. WestJet wants the government to do more to change that
WestJet is asking the federal government to put measures in place to lower ticket costs for travellers, but questions remain on who would foot the bill.
Hundreds have applied for this 'adventurer' job in Banff National Park
Coined as Banff's 'ultimate summer job,' the Moraine Lake Bus Company says hundreds of people from across the world have applied for its adventurer position.
Dangerous brew: Ocean heat and La Nina combo likely mean more Atlantic hurricanes this summer
Get ready for what nearly all the experts think will be one of the busiest Atlantic hurricane seasons on record, thanks to unprecedented ocean heat and a brewing La Nina.
U.S. senators write to Trudeau asking him to meet 2% GDP defence spending commitment
A bipartisan group of 23 U.S. senators have written to Prime Minister Justin Trudeau urging his country to live up to its commitment to spend 2 per cent of GDP on defence amid concerns that key members of the NATO alliance are not pulling their weight.
Potential tornado 'surreal' for residents who witnessed damaging storm in southern Ontario
Witnessing a potential tornado was 'surreal' for residents who caught a glimpse of the damaging storm in southern Ontario on Wednesday night.