'We are not ready to start trial running': OC Transpo will not commit to opening date for Trillium Line
The head of OC Transpo will not commit to opening the new Trillium Line ahead of back-to-school at Carleton University this fall, as testing continues on Ottawa's new north-south light rail transit line.
OC Transpo and its partner TransitNEXT are in week two of the eight to 10 week testing and trial running period ahead of the launch of the LRT line.
OC Transpo management provided a technical briefing on the work being done on Ottawa's new transit line that will run between Bayview Station and Riverside South, with a spur to the Ottawa International Airport. There is also no word on when the new Trillium Line will open for the public.
- Sign up now for daily CTV News Ottawa newsletters
- The information you need to know, sent directly to you: Download the CTV News App
While you see trains running on the line every day, OC Transpo general manager Renee Amilcar would not say when the 21-day testing period will begin.
"We have achieved many significant milestones and made important progress towards this point, but there's still critical work to be done," Amilcar told councillors and the media.
"Throughout trial running, we want to ensure the system is safe and reliable when it opens. This is an important step in our commitment in providing a transit system we can trust."
The 21-day trial running period will be the final step before the Trillium Line launches for passengers, and is included in the eight-to-10 week window before a possible launch.
When asked by Coun. Shawn Menard about a possible opening date ahead of the start of the school year at Carleton University, Amilcar would only say OC Transpo is at the start of the eight-to-10 week testing and trial running period.
"The reason why we don't want to provide any dates is we don't want to work under pressure, and unfortunately give up our good work we have done so far," Amilcar said.
"We have a scenario where we need eight to 10 weeks. I would say we are at the beginning of those eight to 10 weeks, hopefully if everything is OK, after 10 weeks we should have good news to announce. But, today I won't provide any date."
OC Transpo and TransitNEXT began testing and commissioning in June, which includes demonstrating required headways and trial running performance testing, checking vehicle systems and communications systems and train controls. The Trillium Line is now running 18 hours a day during the week, matching planned schedules when the system launches for the public.
"Now we want to run that full schedule for eight to 10 weeks and make sure nothing new arises during that period," Michael Morgan, Director of Rail Construction, said Thursday.
The Trillium Line was originally scheduled to open in August 2022, but the launch is two years behind schedule to construction delays.
Morgan told councillors there are nine prerequisites for trial running:
- The integrated System Infrastructure has been tested.
- The complete fleet is fully tested and ready for passenger service.
- The complete signalling and train control system is fully tested and ready for service.
- The are no outstanding defects affecting rail systems (track, signals and communications)
- There are no major defects, safety defects, or incomplete vehicle modification programs.
- All stations are substantially complete with only minor deficiencies remaining.
- TransitNEXT is fully mobilized, fully trained and ready to commence maintenance.
- TransitNEXT has submitted the Maintenance Verification and Validation Matrix.
- The city is fully mobilized, trained and ready to operate the system.
"We don't want to start trial running prematurely," Morgan said.
OC Transpo continues training diesel rail operators and diesel rail controllers. Forty-seven operators are now trained, with 10 more in progress.
Building occupancy permits have been issued for eight of the 13 stations and the maintenance storage facility.
As part of the pre-launch, OC Transpo and TransitNEXT are required to do a 21-day testing period before the system can launch. The 21-day period includes a 14-day service reliability test with the Trillium Line running a full regular service schedule to simulate passenger service and a seven-day "failure scenario management" period.
"There's a number of things we need to do," Morgan said. "We are not ready to start trial running today."
Within the 14-day simulated passenger service, the minimum on-time performance will be 98.5 per cent over the two-week period.
Morgan told councillors, "the contractor has been very good, totally aligned with us on the idea that we should not start trial running until we're ready."'
Council will receive a daily summary of the trial running period Monday to Friday, including a list of any "critical issues" discovered during the trial period.
CTVNews.ca Top Stories
Sparks fly as MPs question minister on pension implications of proposed election date change
Sparks flew at a parliamentary committee Thursday as MPs questioned Canada's democratic institutions minister about a widely opposed provision in electoral reform legislation that seeks to delay the next fixed election date by one week.
'There is no electricity': Canadian travellers in Cuba urge caution in hurricane's wake
Cuba's power grid was knocked out by Hurricane Rafael, which ripped across the country as a Category 3 storm. In western Cuba, it toppled buildings and pushed 50,000 people to find shelter elsewhere. Cubans were already enduring rolling blackouts due to energy shortages.
Three charged in One Direction singer Liam Payne's death
Three people have been charged in relation to One Direction singer Liam Payne's death in a fall from his Buenos Aires hotel balcony last month, Argentine authorities said on Thursday.
RCMP already 'on high alert' for potential wave of migrants after Trump election
Canada's federal police force has been preparing for months on a contingency plan for a potential massive influx of migrants across the border following Trump's promise of 'mass deportations' of millions of undocumented immigrants in the U.S.
'There was no stopping this baby from coming': Woman gives birth while aboard Newfoundland ferry
A young family from Codroy Valley, N.L., is happy to be on land and resting with their newborn daughter, Miley, after an overwhelming, yet exciting experience at sea.
Volkswagen models recalled for airbag safety precaution
Recall notices have been issued for some Volkswagen models from 2006 to 2019 for airbag safety issues.
Canmore wildlife and landscape defender Karsten Heuer dies peacefully at 56
Canmore conservationist Karsten Heuer, who was a biologist, park ranger, author and activist, has died.
America votes: How celebrities are reacting to Trump's decisive victory
Celebrities from Hulk Hogan to Ariana Grande are sharing their reactions to the U.S. election, which will see Donald Trump return to the White House.
3 Winnipeg police officers charged with breach of trust, theft
Three members of the Winnipeg Police Service have been charged with breach of trust, obstruction of justice and theft following a lengthy investigation