Ottawa LRT is safe, city's transit head vows after TSB concerns
Ottawa's head of transit services vows the city's LRT system is safe after the federal transportation watchdog warned of ongoing safety risks.
"I want to be perfectly clear: the safety of our customers and my team is the number one priority," Renee Amilcar told the first-ever meeting of Ottawa's LRT subcommittee on Thursday.
"The O-Train is safe. If for any reason we believed that the train wasn't safe, we would not operate it."
In a letter dated Feb. 3 and released Wednesday, Transportation Safety Board issued a warning about the axle bearing assembly on Ottawa's Confederation Line trains. Problems with the assembly led to a derailment in August 2021 and additional problems in July 2022.
The TSB said the parts will "continue to pose a risk to safety" until OC Transpo and Rideau Transit Maintenance resolve the issues "to protect the travelling public."
Amilcar told councillors on Thursday that when OC Transpo received the letter, they took the time to review it and organize a meeting with Rideau Transit, Alstom, Rideau Transit Maintenance and the TSB to go over it and ensure the city had full clarity about the TSB's concerns.
"We have thoroughly reviewed the letter and ensured that the enhanced system safety measures currently in place align with the TSB suggestions," she said. "I can assure you that all the measures are in place …to ensure a safe and reliable train system," she said.
"I personally took the train yesterday from my house to the office," she added. "If I thought it was not safe, I would not have used it."
Amilcar also reiterated that the recent settlement with RTG included a plan of action to address the TSB's recommendations, and that RTG has provided written confirmation to the city that the system is safe.
"We asked for this letter," she said.
OC Transpo looking into heat detection
City staff shed more light on why they haven't installed a heat detection system on the trains despite the TSB's suggestion.
In September 2021, several weeks after the derailment caused by an "undetected catastrophic roller bearing failure" in the assembly, the agency recommended OC Transpo and RTM install heat detection systems to monitor temperatures of the assembly.
However, the TSB said this month "no concrete steps have been taken to resolve the safety deficiency identified" in that Rail Safety Advisory.
On Thursday, the city's director of engineering said the technology that exists wouldn't be suitable for light rail trains.
"Heat detection technology is common and familiar within Canada and across North America, but it is common within heavy freight," Richard Holder said. "As far as we are aware, there are no examples of heat detection being employed on a light rail system."
He also said in the case of the August 2021 derailment, the heat detection system would have been too late to prevent the derailment.
"Even if heat detection had been in place at that time, and provided a trigger that the axle was getting hot, it would have been too late," he said. "The failure would have occurred. That has been the position for many, many months."
Instead, the city and RTG implemented a pilot project to test an on-board sensor to measure vibration to provide early-warning signals, rather than heat.
However, the TSB's recent letter has changed that stance. The TSB found that elevated heat led to the bearing failure in July 2022, when an operator felt unusual vibration on a train.
As a result, the city is "actively looking now at what heat detection technologies are out there that we can apply to a light rail system," Holder said.
Current measures not sustainable
Right now, maintenance staff inspect the parts every 7,500 kilometres and replace them every 175,000 kilometres. They are supposed to last 1.2 million kilometres.
Trains are also inspected every morning. There are also temporary speed restrictions on several stretches of the track—particularly curves—to reduce the overall forces on the axles.
But Amilcar admitted those measures aren't sustainable for the long term.
"With the risk, comes mitigation measures, and we have the measures in place- but they are not sustainable in the long term, because we need a lot of workmanship, and we want to make sure we have a final fix in order to apply to the entire fleet and Stage 2," Amilcar said.
OC Transpo playing "catch up" with axle bearings
What is causing the issues with the axle bearings still isn’t clear.
Holder says RTG is still trying to figure out the cause.
"The purpose of that root cause analysis is to determine precisely what are the causes for the failures that we have been seeing," Holder said.
"There is an overall understanding that it is going to be related to the design of the axle, to the conditions on the track, to the geometry of the track. There is an interaction at play between the boogies, the vehicles, and the track infrastructure that is causing this overall issue of the failures of the materials."
Holder says, "Once we have a root cause analysis, which identifies what the problem is, an action plan will be created to make changes both on the track side but also on the vehicle side."
Holder says the city has taken measures to fix problems on the rails and says problems will always occur on a large-scale project like the LRT.
"There always will be measures in place to ensure the safety of the travelling public, so there are hazards and risks associated with huge infrastructure projects, such as the LRT project. We are constantly responding to how the system is performing and if we need to make changes to the system, we will do that."
However, Holder admits the city is playing "catch up" with the axle bearings.
"You are correct to say we are in 'catch up' mode now with the axle bearing issue. But the plan is to find a solid solution so that we have a permanent fix."
Despite the constant problems with the trains, Amilcar says there are no plans to replace the trains.
"At this time, I have no reason to think we have to change the train, but at the end of the day it is Alstom who will make that decision because it is their vehicle," Amilcar said.
"I think it is more important than ever to have a root cause analysis to make sure the final decision is the right one."
Michael Morgan, director of the city’s rail construction, says lesson learned from issues on Stage 1 have already led to changes with Stage 2 construction.
"We have made design changes generally from lessons learned in Stage 1, they are incorporated. The things that may come out of the root cause, like the profile of the railhead- you could update with a rail grinder," Morgan said. "So the fixes that we are talking about with the geometry or wheel-rail interface could be applied to the infrastructure so we are going ahead and building the infrastructure. If we need to come back with a grinding machine and fix that, we will."
But Morgan says there are no plans to "rip up the track".
Morgan says, "The track uses standard rails, standard ties, standard clips- it is a standard design. The changes that you make, or that we have been looking to make out of Stage 1, are adjustment to the rail neutral temperature – so the laying temperatures of the rail, to be able to deal with the hot summers; making sure the foundation, the ballast is built corrective to deal with tight curve. Those are all things we are applying to Stage 2, there is no obvious path forward to having to rip up the tracks completely."
CTVNews.ca Top Stories
Thinking about quitting social media? There may be another option, B.C. researcher says
Strategies for mitigating the negative mental health effects of social media tend to focus on reducing time spent scrolling, according to a B.C. researcher, who says there may be a way to limit the harm without logging off.
Trudeau says he could have acted faster on immigration changes, blames 'bad actors'
Prime Minister Justin Trudeau says the federal government could have acted faster on reining in immigration programs, after blaming 'bad actors' for gaming the system.
Prince Harry makes surprise Grey Cup appearance in Vancouver
Prince Harry surprised football fans Sunday, appearing at the Grey Cup in Vancouver before the Toronto Argonauts took on the Winnipeg Blue Bombers.
Father, 2 children missing from northern B.C may be travelling to Alberta: RCMP
Mounties in B.C. are asking the public for help locating a father and his two children who have not been seen since Friday.
Biden authorizes Ukraine's use of U.S.-supplied long-range missiles for deeper strikes inside Russia
U.S. President Joe Biden has authorized Ukraine to use U.S.-supplied long-range missiles to strike deeper inside Russia, easing limitations on the weapons.
Apparent Taylor Swift ticket scam targets hundreds who claim to be out $300K
An apparent scam allegedly targeting roughly four hundred people, many of whom based out of Burlington, Ont., claim to be out approximately $300,000 in total after believing they were purchasing Taylor Swift tickets in Toronto, but never receiving them.
E. coli outbreak linked to organic carrots leaves 1 dead and dozens sickened across the U.S.
The US Centers for Disease Control and Prevention is investigating an E. coli outbreak in at least 18 states linked to some organic carrots, which has led to at least one death.
Toronto Argonauts, Winnipeg Blue Bombers begin battle as 111th Grey Cup kicks off
The 111th Grey Cup has kicked off at B.C. Place Stadium with the Toronto Argonauts facing the Winnipeg Blue Bombers.
Dwayne Johnson's US$200 million+ Christmas pic opens to US$34.1 million
Moviegoers were not exactly feeling the Christmas spirit this weekend, or at least what 'Red One' was offering. The big budget, star-driven action comedy with Dwayne Johnson and Chris Evans sold US$34.1 million in tickets in its first weekend in theaters, according to studio estimates Sunday. It easily topped a box office populated mostly by holdovers.