Trillium Line will undergo 21 consecutive days of testing before launch
The city of Ottawa will require a longer trial run period for the new north-south Trillium Line before it launches, incorporating lessons learned from the launch of the Confederation Line nearly three years ago.
The city of Ottawa released the unredacted versions of the Stage 2 O-Train Confederation Line and Trillium Line Project Agreement Testing and Commission Schedules on Friday. The documents outline the testing and commission and trial running before launching Stage 2 of the LRT projects.
In a memo to council, Director of Rail Construction Program Michael Morgan said lessons learned from the commissioning and trial running of Stage 1 of the Confederation Line will be implemented into Stage 2 Trillium Line requirements.
"Staff applied various lessons learned from the testing and commissioning and trial running of the Line 1 Confederation Line into the Stage 2 Trillium Line extension requirements, including longer trial running period, improved performance criteria and inclusion of a systems integration verifier to oversee the works," Morgan said.
The Confederation Line will be required to undergo 12 consecutive days of testing before launch, while the Trillium Line from Bayview Station to Riverside South will undergo 21 consecutive days of testing.
Morgan says there will be a trial running period of 14 days for the Trillium Line, with an additional tests "during the 21 day period" that would include "a variety of failure management scenarios that could reasonably be expected to occur."
OC Transpo and Rideau Transit Group were required to conduct 12 days of testing before the Confederation Line opened from Blair Road to Tunney's Pasture in 2019. The city of Ottawa took possession of the Confederation Line on Aug. 23, 2019, 456 days after the initial deadline.
Here is a look at the Testing and Commission schedules for the Stage 2 LRT.
TRILLIUM LINE
TransitNEXT will be responsible for the testing and commissioning of the complete integrated system (civil infrastructure, systems, vehicles, etc.)
Morgan says TransitNEXT will conduct trial running when the integrated system infrastructure has been tested, when the complete fleet is fully tested and ready for messenger service, there are no outstanding defects affecting rail system functionality and all stations "are substantially complete with only Minor Deficiencies remaining."
The trial run length will be 21 days, with the trial run operating a full regular scheduled service on the full line for a 14-day period.
Additional tests during the 21-day period will include a variety of failure management scenarios that could "reasonably be expected to occur in regular revenue service," Morgan said.
The performance criteria is TransitNEXT achieving the Service Reliability Standard wherein 98.5 per cent on-time performance must be achieved over a 14-day period within the 21-day Trial Running period.
"TransitNEXT will demonstrate that the integrated system (vehicles, stations, and infrastructure) performs reliably through the Trial Running period such that the performance criteria for Trial Running are achieved and that would otherwise lead to zero performance deductions during the maintenance period," said the memo.
CONFEDERATION LINE
The city of Ottawa says Rideau Transit Group is responsible for the testing and commissioning of the complete integrated system (civil infrastructure systems, vehicles, etc.)
"RTG is responsible to conduct trial running when the integrated system has been tested and is essentially ready for revenue service," writes Morgan.
"Trial running will be the final step in confirming readiness for revenue service."
The 12 consecutive days of trial running will operate a full regular scheduled service on the full line using the peak and non-peak schedules for an "extended period," the city says.
"The tests will include a variety of failure management scenarios that could reasonably be expected to occur in regular revenue service," Morgan said.
The Confederation Line extension will run from Blair Road to Tenth Line Road in the east end, and from Tunney's Pasture to Algonquin College and Moodie Drive in the west end.
CTVNews.ca Top Stories
'It could be catastrophic': Woman says natural supplement contained hidden painkiller drug
A Manitoba woman thought she found a miracle natural supplement, but said a hidden ingredient wreaked havoc on her health.
WATCH Video shows dramatic police takedown of carjacking suspects chased through parking lot north of Toronto
Police have released video footage of a dramatic takedown of a group of teens wanted in connection with an attempted carjacking in Markham earlier this month.
After hearing thousands of last words, this hospital chaplain has advice for the living
Hospital chaplain J.S. Park opens up about death, grief and hearing thousands of last words, and shares his advice for the living.
DEVELOPING G7 warns of new sanctions against Iran as world reacts to apparent Israeli drone attack
Group of Seven foreign ministers warned of new sanctions against Iran on Friday for its drone and missile attack on Israel, and urged both sides to avoid an escalation of the conflict.
WHO likely to issue wider alert on contaminated cough syrup
The World Health Organization is likely to issue a wider warning about contaminated Johnson and Johnson-made children's cough syrup found in Nigeria last week, it said in an email.
Tesla recalling nearly 4,000 Cybertrucks because accelerator pedal can get stuck
Tesla is recalling 3,878 of its 2024 Cybertrucks after it discovered that the accelerator pedal can become stuck, potentially causing the vehicle to accelerate unintentionally and increase the risk of a crash.
'It was all my savings': Ontario woman loses $15K to fake Walmart job scam
A woman who recently moved to Canada from India was searching for a job when she got caught in an online job scam and lost $15,000.
A couple lost their wedding rings during the ceremony. Two strangers found a fitting solution
Every good wedding has to have one teensy, tiny crisis.
Families to receive Canada Child Benefit payment on Friday
More money will land in the pockets of some Canadian families on Friday for the latest Canada Child Benefit installment.