Renfrew, Ont. town council failed to properly scrutinize Ma-Te-Way expansion: report
A new report into the multi-million-dollar Ma-Te-Way Centre expansion project says the Town of Renfrew council failed to properly scrutinize the controversial and costly venture.
The expansion of the Ma-Te-Way Centre was originally expected to cost $18 million, but the final report prepared by WSCS Consulting into the decisions that led to the project's cost overruns says the development has ballooned to $38.7 million and will leave Renfrew taxpayers footing the bill for decades.
Renfrew approved a process to replace the aging recreation centre to build the expanded Ma-Te-Way Centre, which included the addition of a second ice pad, a walking track, gymnasium, fitness centre and multicultural hub. The town obtained more than $11 million in grant funding from the federal and provincial governments in 2020 and awarded a construction contract in 2021.
- Sign up now for daily CTV News Ottawa newsletters
- The information you need to know, sent directly to you: Download the CTV News App
The original budget was $18 million. The report states that the budget was unrealistic from the outset.
"Even though every tender and proposal came in over budget, the Town insisted on presenting it based upon its set budget as if to say that it did not believe the contractors or consultants. This was a major failing and likely resulting in the loss of $7M in potential grant funding. Even though estimates showed that the project would likely cost $23-25M, the Town submitted the grant application for $16M and received $11.8M in funding."
The report says a lack of oversight by the town council and the project director led to flawed financial strategy and analysis.
"Council placed an unreasonable and ill-informed amount of confidence in the former Director of Parks and Recreation without understanding the implications at a time of organizational restructuring. Consequently, Council allowed the Director to make decisions with respect to design, scope, partnerships and construction tenders without approval or oversight. Weak internal controls allowed for inappropriate transactions to be approved, conflict of interest and Town policies, code of conduct and bylaws violated," the report says.
"Council did not insist on regular written reporting, did not challenge the Director nor the Treasurer on key financial statements/presentations nor did it require variance and risk analysis be undertaken, leading to cost overruns. Presentations went so far as to imply there would be a ‘surplus’ created by debenture funds (a liability)."
The project is now 115 per cent over budget, according to the report, coming in at an estimated $38.7 million — another $3 million higher than figures provided in late 2023.
The report by WSCS Consulting says the price tag is an estimate, with the full costs not known as it's not "fully complete and the facility is not fully occupied." It also notes interest costs will add $15 million to the cost, and there is about $5 million in "unfunded expenses."
"The Town's taxpayers will be bearing the financial burden of this project for the next 30 years," the report states, adding the cost overruns will need to be financed with debt and taxes.
"The Town will need a strategy to become open, transparent and accountable to its taxpayers and demonstrate it can and will make the changes needed to ensure that a failure of this nature never happens again."
The report makes 46 recommendations, including implementing a project management model requiring monthly written reports to council, creating an audit committee and hiring a professional project manager for major projects.
“In short, some stakeholders wanted the Ma-te-Way Expansion to proceed and policies, processes and laws were ignored to make it happen without regard to what it would cost," the report says.
In April, council voted to refer the third-party review into the expansion project to the Ontario Provincial Police.
On March 26, council voted 5-1 to call on Mayor Tom Sidney to resign, with council expressing concerns over the mayor's handling of the expansion of the Ma-Te-Way Activity Centre. SIdney vowed to stay on the job. Before being elected mayor, Sidney spearheaded the expansion project for the Ma-Te-Way Activity Centre as chair of the recreation committee.
With files from CTV News Ottawa's Josh Pringle
CTVNews.ca Top Stories
BREAKING At least nine killed, 300 hurt after second wave of device explosions is reported in Lebanon
Explosions went off in Beirut and multiple parts of Lebanon in an apparent second wave of detonations of electronic devices, Hezbollah officials and state media said Wednesday, reporting walkie-talkies and even solar equipment detonating a day after hundreds of pagers blew up.
BREAKING First Conservative motion attempting to bring down Liberals to simply ask if House has confidence in Trudeau
Conservative Leader Pierre Poilievre has confirmed his party is putting forward a non-confidence motion next week and the wording is very straight forward.
Record-breaking Lotto Max jackpot tickets sold in Ontario, Quebec
Two lucky people in Ontario and Quebec will split Tuesday’s record-breaking $80-million Lotto Max jackpot.
Rogers Communications to buy out Bell's share of MLSE for $4.7 billion
Rogers Communications Inc. is buying out Bell's 37.5 per cent share of Maple Leaf Sports & Entertainment for $4.7 billion, giving it 75 per cent ownership of the sports conglomerate.
BREAKING Transport Minister Pablo Rodriguez to step down, will stay on as MP
Federal Transport Minister Pablo Rodriguez is set to announce he’s stepping down from cabinet and as the Quebec lieutenant on Thursday, but he’ll remain an MP, CTV News has confirmed.
'I thought I was dead': Man electrocuted, burned at SaskPower hydro dam calls for compensation
May 9, 2022 was the day Blayne McKay thought he was going to die. He called his wife to say goodbye, after getting electrocuted at the SaskPower Island Falls Hydroelectric Station, about 100 kilometres northwest of Flin, Flon.
8-year-old Ohio girl takes her family's SUV, drives to Target
An 8-year-old girl took an SUV from her Ohio home and drove for miles to a store where she was later found unharmed, authorities said.
Affordability crisis could be reaching its peak in Canada, economist says
With Canada's annual inflation rate reaching the central bank's two per cent target, the country's affordability crisis could be peaking, according to an economist.
Catherine, Princess of Wales, goes back to work days after cancer treatment update
Catherine, Princess of Wales has held her first engagement since revealing that she has completed her chemotherapy treatment.