OC Transpo to open Trillium Line in three stages starting Jan. 6
The City of Ottawa will ring in 2025 with the launch of its new north-south light-rail transit line, but service will only be five days a week on the Trillium Line during the first phase of launch.
OC Transpo general manager Renee Amilcar announced a three-phase approach to opening Line 2 and Line 4, officially opening service to the public on Jan. 6.
"I'm confident that OC Transpo and our maintainer, TransitNext, are ready for the new challenges of revenue service," Amilcar told reporters and councillors on Friday.
"I'm confident in the system."
- Sign up now for daily CTV News Ottawa newsletters
- The information you need to know, sent directly to you: Download the CTV News App
The Trillium Line will run between Bayview Station and Limebank Station, with a spur connecting South Keys Station and the Ottawa Airport. The Line 2 and 4 were originally scheduled to open in August 2022.
Amilcar says the Trillium Line will open in three phases, starting with five-day service Monday to Friday beginning Jan. 6 for a minimum of two weeks.
"This phased launch approach will help ensure customers have time to build their familiarity with the system, improve service reliability, and allow for comprehensive staff training," Amilcar said.
"In addition, launching a major system change in the winter is not a common practice in the transit industry as the inclement weather adds extra complexity to operations teams and for customers. The phased in opening of Lines 2 and 4 will assist our team to better prepare to manage any service disruptions."
The three phase approach will look like this:
- Phase 1: Lines 2 and 4 will run Monday to Friday for five-day service for a minimum of two weeks. Parallel bus service will continue to run during this phase.
- Phase 2: Six-day service for a minimum of two weeks.
- Phase 3: Lines 2 and 4 will operate on a seven-day schedule.
"Once the system demonstrates the performance we expect, then we will expand to the next phase of service," Amilcar said.
OC Transpo will continue to run parallel bus service along the Trillium Line during the launch period.
"It will only be gradually reduced when it's clear it is no longer required," Amilcar said.
The line has undergone extensive testing and recently passed its trial running phase with a 99.5 per cent grade during the 14-day trial running period. Staff say issues were identified with the vehicle, signals and the track during the testing and trial running.
"During this time there were three types of issues that impacted TransitNext's 99.5 per cent on-time performance. Overall, it amounted to 26 trips out of 4,850 trips that were delivered by TransitNext as planned," Richard Holder, director of Rail Construction Program, said.
"When issues were identified, our teams worked collaboratively with TransitNext to make adjustments where possible and enhance service delivery."
A presentation prepared for the city's LRT subcommittee meeting last Friday said there was still some work to be done, including additional drills, winter performance preparations, a roll out of customer information and continued training for operators.
Holder said there is still a number of "outstanding work" to address in the weeks ahead before launch and into the new year. The issues include:
- Switch enhancements at Gladstone
- Hot box detection
- Hunt Club Road work
- Modifications to train bell ringing volume
- Building reliability of passenger information displays
- Replacement of a defective sensor in elevators. Holder said there are "several" defective sensors in elevators.
OC Transpo says over the coming weeks, system preparations will include additional drills to practice scenarios employees will face during regular service, continued training of Diesel Rail Operators and "ongoing operation of the line exercising all aspects of daily service including launch and reduction of trains."
Amilcar was asked by Coun. Riley Brockington why OC Transpo is conducting a phased-in approach to running the Trillium Line after months of testing.
"We have to continue to learn. It's something to run trains for years, it's another thing to run trains with a timetable with nine trains daily, with all of the systems," Amilcar said, adding she has spoken to experts from around the world about the launch.
"This approach is the best approach to make sure that we build the confidence, that we build the reliability and then people will come."
Line 2 and 4 will run 6 a.m. to 12 a.m. Monday to Friday.
Line 2 will cover 19 km between Bayview and Limebank stations, passing through 16 neighbourhoods and Carleton University. Line 4 will run between South Keys Station and the Ottawa Airport, including a stop near the EY Centre.
CTVNews.ca Top Stories
![](https://www.ctvnews.ca/polopoly_fs/1.7173593.1736789292!/httpImage/image.jpg_gen/derivatives/landscape_800/image.jpg)
Norovirus cases are rising in Canada. Here's advice from a doctor
Canadian health officials are reporting a rising number of cases of the highly contagious norovirus disease in Canada, warning that the elderly and young children are most at risk.
Canada and U.S. warships join forces in South China Sea through contested waters
The United States Navy's USS Higgins joined HMCS Ottawa in the South China Sea, near the contested Scarborough Shoal, on Thursday. The two warships travelled south together towards the Spratly Islands – a number of which China has militarized.
Alberta premier talks about 'tariff-free relationship' with the U.S.
Alberta Premier Danielle Smith said her conversations with U.S. President Donald Trump went well, but the leader's tariff threat has not been averted.
Progress made in talks over Israel-Hamas ceasefire and hostage release, officials say
U.S. and Arab mediators made significant progress overnight toward brokering a ceasefire in the Israel-Hamas war and the release of scores of hostages held in the Gaza Strip, but a deal hasn't been reached yet, officials said Monday.
Bishop's students allege teacher uses degrading terms, university doing nothing
Students at Bishop's University in Sherbrooke, Que., say they're shocked and appalled by the school's apparent lack of action over a teacher they allege has been using derogatory language in her classroom for years.
Canada Post stamps just got more expensive
Canada Post is raising the price of stamps, starting today. Stamps purchased in a booklet, coil or pane will cost 25 cents more at $1.24 per stamp. The price of a single domestic stamp is now $1.44, up from $1.15.
Teenager stabbed during altercation inside Hillcrest High School
Two people were seriously injured during an altercation at an Ottawa high school on Monday morning.
Ottawa driver's Jaguar SUV held for months during dispute between tow truck company, insurance provider
An Ottawa driver is speaking out after her vehicle was towed from a crash scene in early November and held for months during a dispute between a local tow truck company and insurance provider.
Weekend announcements narrow field of high-profile Liberal leadership prospects
As a race to elect a new Liberal leader quickly approaches, a high-profile candidate appears set to throw their hat into the ring.