Despite missing two deadlines, the consortium building the $2.1 billion Confederation Line LRT is confident of meeting a March 31 handover date to the City of Ottawa.
OC Transpo boss John Manconi is still being cautious and told councillors Tuesday he is 'highly skeptical' that Rideau Transit Group will meet the March deadline
RTG CEO Peter Lauch appeared before the city's finance and economic development committee to assure councillors of the progress made in construction and testing of the LRT system.
More to come.
Manconi tells Councilllor Deans he is “highly skeptical” RTG will make March 31 deadline. He says he’s happy to be wrong but is concerned. @ctvottawa #ottnews
— Joanne Schnurr (@JoanneCTV) February 12, 2019
RTG hopes to do a 12 day consecutive test run second week of March @ctvottawa #ottnews