The city of Ottawa says labour and supply chain issues are putting pressure on finishing the western extension of Stage 2 LRT on time.
Kiewit-Eurovia-Vinci (KEV) is the construction consortium contracted with the extension of the Confederation Line. Director Chris Loeffler says, “At this time, we are still analyzing the schedule,” when asked whether the line would be completed by the target date of 2025.
Ottawa’s Stage 2 LRT will extend west from Tunney’s Pasture to Moodie Drive. In the east it will connect Blair Road to Trim Road.
Loeffler says, “In the west (extension), we have some real challenges, we have some geotechnical issues as well some other supply issues. We have had a hard getting enough manpower, we are bringing in a lot of carpenters and workers from other provinces to help out with that.”
This comes as the city marks a milestone for the eastern extension. Rail tracks have arrived and are being laid just past Blair station near Jeanne d’Arc Boulevard. The target completion date is 2024.
Loeffler says despite labour and supply issues, the eastern extension is on time. “As we look to the east, we expect to be on time. We are having a hard time getting some of our supplies out of different areas, some supply chain problems that we are seeing, we are working through those as they come but, all things considered, we look to be on time in the east.”
Mayor Jim Watson says the city will not commit to a specific completion day, “We learned a long time ago if we put in a specific date or month and we miss it by one day, we are better to just say 2024, and 2024 goes until December 31.”
Watson says, “This is a very important day and date for the people in the east, they have proven time and time again to be the best transit users on a per-capita basis than any part of the city. This is going to give them more of a faster, reliable transit service.”
In December, the city learned the extension of the Trillium line to Riverside South as part of Stage 2 will be delayed by nine months, and now has a target completion date of May 2023.
Stage 2 LRT comes with a price tag of $4.6 billion dollars and will be funded by the federal government, the province, and the city.
Despite the challenges, Watson says the project is still on-budget. “We are very fortunate we assigned the contract, which was a fixed price contract, prior to the pandemic. We are very fortunate to get that contract in under the wire, so the prices are fixed.”
CTVNews.ca Top Stories
Several dead in Copenhagen mall shooting; suspect arrested
A gunman opened fired inside a busy shopping mall in the Danish capital on Sunday, killing several people and wounding several others, police said.

'Be prepared for delays at any point': Canada not flying alone in worldwide travel chaos
As Canadian airports deal with their own set of problems amid the busy summer travel season, by no means are they alone.
Alpine glacier chunk detaches, killing at least 6 hikers
A large chunk of Alpine glacier broke loose Sunday afternoon and roared down a mountainside in Italy, sending ice, snow and rock slamming into hikers on a popular trail on the peak and killing at least six and injuring eight, authorities said.
Blue Jays mourn death of first base coach Mark Budzinski's daughter
First base coach Mark Budzinski is taking a leave of absence from the Toronto Blue Jays following the death of his daughter.
Dog left with lost baggage at Toronto Pearson Airport for about 21 hours
A Toronto woman says a dog she rescued from the Dominican Republic has been traumatized after being left in a corner of Toronto Pearson International Airport with baggage for about 21 hours.
'There should have been one': N.S. mother drives son to ER after waiting nearly an hour for ambulance
A Nova Scotia mother says she had to drive her son to hospital herself on Canada Day when no ambulance showed up after more than 40 minutes.
'Cold-adapted' dinosaurs survived mass extinction event to achieve dominance, study finds
A new study has offered what it says is the first physical evidence showing dinosaurs from the Triassic period regularly endured freezing conditions, allowing them to survive and eventually supersede other species on the planet.
Vancouver police service dog named after Calgary police officer
A Vancouver Transit Police service dog has a special connection to the Calgary Police Service.
'Ungrading': How one Ontario teacher is changing her approach to report cards
An Ontario high school teacher plans to continue with an alternative method of grading her students after an experiment last semester in which students proposed a grade and had to justify it with examples of their work.