LRT Trillium Line scores near perfect in first week of testing

A Trillium Line train parked at South Keys Station on Thursday, May 16. (Leah Larocque/CTV News Ottawa) A Trillium Line train parked at South Keys Station on Thursday, May 16. (Leah Larocque/CTV News Ottawa)
Share

The first of week of testing for Ottawa's new north-south line is going as well as hoped.

Testing began one week ago for a 14-day trial run of the Trillium Line. TransitNEXT, the consortium that built the line, needs to meet a minimum 98.5 per cent on-time performance rating during the daily testing period.

As of Sunday's trial testing, the 14-day rolling average stands at 99.6 per cent. 

Despite a few issues on some vehicles this week, none of the problems dramatically affected the on-time performance of the new diesel trains.

Reliability scores released daily by OC Transpo have reached perfect or near-perfect marks, with trial running still set to conclude on Oct. 21.

The 14-day reliability testing period simulates the conditions of normal passenger service and will be followed by a seven-day second phase that looks at daily operational and maintenance scenario evaluations.

On-time performance is measured by assessing on-time departures at terminus stations for both Lines 2 and 4 – Bayview and Limebank Stations on Line 2, and South Keys and Airport stations on Line 4. Trains must depart within 30 seconds of their scheduled time.

If the 21-day testing period runs smoothly, the Trillium Line could open to the public in mid-November.

The 16-kilometre, north-south line was originally scheduled to open to the public in August 2022.

Here is a summary of the first week of testing:

 

Day 1: Monday Oct. 7

The Trillium Line had an on-time performance of 98.3 per cent on the first day of testing, just short of the 98.5 per cent rolling average required over the 14-day trial.

Key issues identified that caused the lower score included a minor braking issue on one of the trains and a software problem with CCTV camera functionality on two others.

 

Day 2: Tuesday, Oct. 8

The second day of testing had an on-time performance of 99.4 per cent, bringing the 14-day rolling average to 98.9 per cent. Four trains left their stations over the 30-second mark required to be considered on-time.

Among the key issues identified were another CCTV camera software problem on one of the trains.

 

Day 3: Wednesday, Oct. 9

The third day of testing had its first perfect score, with 100 per cent of the trains leaving on-time. The successful trial testing brought the 14-day rolling average to 99.3 per cent.

 

Day 4: Thursday, Oct. 10

The fourth day of testing had a perfect score, bringing the 14-day rolling average to 99.4 per cent.

 

Day 5: Friday, Oct. 11

The Trillium Line had an on-time performance of 99.4 per cent on the fifth day of testing, keeping the 14-day rolling average to 99.4 per cent.

 

Day 6: Saturday, Oct. 12

The sixth day of testing had a perfect score, bringing the 14-day rolling average to 99.5 per cent.

 

Day 7: Sunday, Oct. 13

The seventh day of testing had a perfect score, bringing the 14-day rolling average to 99.6 per cent.

With files from CTV News Ottawa's Josh Pringle

 

  

CTVNews.ca Top Stories

U.S. Congress hosts second round of UFO hearings

The U.S. government held another UFO hearing on Capitol Hill on Wednesday, the second such hearing in 16 months. This hearing was billed as an attempt by congress to provide a better understanding of what is known about previous sightings of UFOs, also known as UAPs (Unidentified Anomalous Phenomena).